Scatter Plot: Cost vs. Duration

Scatter Plot: Cost vs. Duration also known as a Bull’s Eye, Football, or Joint Confidence Level chart, shows a comparison of the Total Project Cost vs. Total Project Duration or Finish Time for each iteration of the simulation and is part of the Project Summary.

To view the Scatter Plot: Cost vs. Duration:

  1. Make sure that your schedule has both uncertainties in duration and cost
  2. Run a Monte Carlo simulation.
  3. Click the Analysis tab. On the Project Summary view, click Cost vs. Duration scatter Plot. The scatter plot opens.
  4. Select type of the plot you want to view:
    • Project Cost vs. Project Duration, or
    • Project Cost vs. Project Finish Time

See also

Viewing sensitivity analysis for each task

Project Summary View