Search found 15 matches
- Wed Mar 20, 2024 9:57 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Sorting Risk Assignments view
- Replies: 1
- Views: 15223
Sorting Risk Assignments view
I can’t get the Risk Register and Risk Assignments to filter in the same order. Also I am unable to insert the Risk ID into the assignments view.
- Wed Mar 20, 2024 9:57 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Low number of Sensitivity Results
- Replies: 1
- Views: 15737
Low number of Sensitivity Results
We have been running simulation on a large schedule, but only seeing a few results in the Sensitivity View. Is there a way to see more results?
- Tue Jul 02, 2019 3:46 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Assigning risks from risk templates to tasks
- Replies: 1
- Views: 29308
Assigning risks from risk templates to tasks
Does loading risks from a risk template into the Risk tab of the Task Information add the risks to the risk register?
- Sun Nov 04, 2018 11:33 am
- Forum: Project Portfolio Risk Management
- Topic: Exporting XML to MS Project
- Replies: 1
- Views: 30264
Exporting XML to MS Project
Is it recommended to export simulation results back to MS Project?
- Sun Nov 04, 2018 11:32 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Using percentiles to calculate management baselines
- Replies: 1
- Views: 21208
Using percentiles to calculate management baselines
What percentiles from your results should you used for your management baseline?
- Fri Jun 19, 2015 2:00 pm
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Cloud Evaluation
- Replies: 2
- Views: 14858
Re: RiskyProject Cloud Evaluation
I have RiskyProject Enterprise 6.1.2.3. What version of RiskyProject Cloud should I use?
- Fri Jun 19, 2015 1:59 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject 6.1.2.3 - Minor Software Release
- Replies: 2
- Views: 15612
Re: RiskyProject 6.1.2.3 - Minor Software Release
When it is current version for RiskyProject?
- Fri Oct 10, 2014 3:37 pm
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Cloud
- Replies: 4
- Views: 20205
Re: RiskyProject Cloud
Does RiskyProject Cloud have a Monte Carlo simulation?
- Sun Sep 29, 2013 4:08 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject for Oil and Gas
- Replies: 5
- Views: 26800
Re: RiskyProject for Oil and Gas
Do you have a separate release of RiskyProject for oil and gas industry?
- Sun Sep 29, 2013 4:04 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Defining Event Chain
- Replies: 6
- Views: 27362
Defining Event Chain
I have RiskyProject 5.0.7.1. I think it is a latest version. I have three risks:
- Bad weather: it triggers
- Equipment delivery: it triggers
- Construction delay
How can I define this chain in RiskyProject?
- Bad weather: it triggers
- Equipment delivery: it triggers
- Construction delay
How can I define this chain in RiskyProject?
- Mon Jan 09, 2012 11:37 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: How to set number of simulations
- Replies: 1
- Views: 14909
How to set number of simulations
Hi,
I am required to run a minimum number of iterations for a simulation. Everytime I run one it seems to finish to early. How do I set the number of iterations in the Monte Carlo Simulation?
Thank you for any suggestions
I am required to run a minimum number of iterations for a simulation. Everytime I run one it seems to finish to early. How do I set the number of iterations in the Monte Carlo Simulation?
Thank you for any suggestions
- Wed May 19, 2010 9:28 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Risk correlations
- Replies: 13
- Views: 62992
Risk relationships parent child
Is it possible to define risk relationships, parent/child etc in RiskyProject. A Risk that can cause additional risks where the first risk is the parent and the second is the child?
- Tue Mar 21, 2006 9:13 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Why export results back to Project
- Replies: 1
- Views: 21713
Why export results back to Project
Why would I need to export results of analysis back to Microsoft Project?
- Fri Mar 10, 2006 1:31 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Short summary of Event Chain Methodology
- Replies: 6
- Views: 43320
- Fri Mar 10, 2006 1:25 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Short summary of Event Chain Methodology
- Replies: 6
- Views: 43320
Short summary of Event Chain Methodology
Could you outline major principles of Event Chain Methodology?