Search found 70 matches

by Ken
Mon Nov 03, 2025 11:18 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Schedule Diagnostics is frozen
Replies: 1
Views: 7929

Schedule Diagnostics is frozen

I am trying to apply the schedule diagnosis to a program with more than 5.000 lines and the software is getting stack. So I would like to know is there a way to solve this issue, or de diagnosis have a limit to work with a number of lines. I am going to try changing the extension of the file because...
by Ken
Thu Oct 23, 2025 3:40 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Schedule Diagnostics Freezing
Replies: 1
Views: 10297

Schedule Diagnostics Freezing

I am trying to apply the schedule diagnosis to a program with more than 5.000 lines and the software is getting stuck. So I would like to know is there a way to solve this issue?
by Ken
Wed Jul 16, 2025 7:41 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Mapping a single probability to each risk category.
Replies: 1
Views: 165095

Mapping a single probability to each risk category.

How do I map probability (cost, schedule, etc.) from my Excel risk register. We only have one probability, where as RiskyProject has probabilities for each risk category. Also, how do I add the cost of the pre-mitigated risk?
by Ken
Tue Nov 12, 2024 11:03 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing Risk Registers into an existing schedule
Replies: 1
Views: 159603

Importing Risk Registers into an existing schedule

Getting odd results after importing a risk register and assigning risks. I can provide the files if you have any suggestions on what might be going on.
by Ken
Fri Sep 06, 2024 2:14 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Trial period expired prior to evaluation
Replies: 1
Views: 153981

Trial period expired prior to evaluation

I wasn't as prepared to use the trial as I thought and could not demo the software properly. Is it possible to extend the trial period now that I am in a better place to do a proper demo?
by Ken
Fri Dec 15, 2023 9:06 pm
Forum: Project Portfolio Risk Management
Topic: Incorrect username or password error message logging onto database
Replies: 1
Views: 166919

Incorrect username or password error message logging onto database

We are having an issue with user authentication in RiskyProject Enterprise. Some users when having not logged onto the system for a couple of months the get an error message “Incorrect username or password”. In addition, we have users who can logon without having to enter their username and password...
by Ken
Fri Dec 15, 2023 9:05 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Inserting new columns to the Risk Register
Replies: 1
Views: 166056

Inserting new columns to the Risk Register

I would like to insert a custom column "Risk Velocity" to the risk register. Is it possible to do it? I could not find this field within a list of standard fields in RiskyProject.
by Ken
Sun Oct 15, 2023 8:21 pm
Forum: Project Portfolio Risk Management
Topic: Adding Incidents
Replies: 1
Views: 167085

Adding Incidents

We are thinking of adding Incident management to our processes. How should we go about it?
by Ken
Sun Oct 15, 2023 8:21 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: How to Enable Incidents
Replies: 1
Views: 166748

How to Enable Incidents

We just purchased RiskyProject Enterprise and noticed that there is Incident management in the Help. However, we have not been able to find it. Is this a separate module that we need to purchase, if not is can we enable somehow?
by Ken
Sun Oct 15, 2023 8:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Incidents vs Issues
Replies: 1
Views: 168382

Incidents vs Issues

I have been reading through your documentation and see that there are both issues and incidents referenced, and both are indicators that a risk has occurred. What is the difference between the two?
by Ken
Mon Aug 07, 2023 12:25 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Project Control in RiskyProject
Replies: 2
Views: 732905

Project Control in RiskyProject

We usually update information about project performance by different teams or users in Microsoft Project as part of our project control procedure. Is it possible to use this information to recalculate the chance that project will be completed on time and on budget in RiskyProject?
by Ken
Mon Jul 03, 2023 10:02 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License Activation Already Activated Message
Replies: 1
Views: 167271

License Activation Already Activated Message

I am getting a license wizard pop up every time I try to use Risky Project. Then I get an error that says this License is already activated, please contact intaver institute for more information. Please advise.
by Ken
Mon Jul 03, 2023 10:02 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Viewing or Converting Labour Days to Calendar Days
Replies: 1
Views: 167261

Viewing or Converting Labour Days to Calendar Days

I have a chronogram and by default RiskyProject by default uses labour days for base duration. I would to show the calendar days. ¿How is it possible to get that?
by Ken
Sat Oct 08, 2022 8:14 pm
Forum: Project Portfolio Risk Management
Topic: Sorting and Filtering columns
Replies: 1
Views: 175971

Sorting and Filtering columns

I am using a trial version of RiskyProject for doing a risk analysis on a project. I am trying to sort activities by activity codes to assign duration uncertainties but do not see any option to do so in the software. I tried to look for tutorial videos on your website but there is nothing that talks...
by Ken
Fri Jun 17, 2022 12:30 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Split Tasks
Replies: 3
Views: 218522

Re: Split Tasks

Also duration and work of split task after import to RiskyProject can be incompatible with duration and work in Microsoft Project and other project management software. However Start and Finish Times of all tasks should be the same.