Search found 67 matches
- Tue Nov 12, 2024 11:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Importing Risk Registers into an existing schedule
- Replies: 1
- Views: 821
Importing Risk Registers into an existing schedule
Getting odd results after importing a risk register and assigning risks. I can provide the files if you have any suggestions on what might be going on.
- Fri Sep 06, 2024 2:14 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Trial period expired prior to evaluation
- Replies: 1
- Views: 2060
Trial period expired prior to evaluation
I wasn't as prepared to use the trial as I thought and could not demo the software properly. Is it possible to extend the trial period now that I am in a better place to do a proper demo?
- Fri Dec 15, 2023 9:06 pm
- Forum: Project Portfolio Risk Management
- Topic: Incorrect username or password error message logging onto database
- Replies: 1
- Views: 15464
Incorrect username or password error message logging onto database
We are having an issue with user authentication in RiskyProject Enterprise. Some users when having not logged onto the system for a couple of months the get an error message “Incorrect username or password”. In addition, we have users who can logon without having to enter their username and password...
- Fri Dec 15, 2023 9:05 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Inserting new columns to the Risk Register
- Replies: 1
- Views: 15334
Inserting new columns to the Risk Register
I would like to insert a custom column "Risk Velocity" to the risk register. Is it possible to do it? I could not find this field within a list of standard fields in RiskyProject.
- Sun Oct 15, 2023 8:21 pm
- Forum: Project Portfolio Risk Management
- Topic: Adding Incidents
- Replies: 1
- Views: 15893
Adding Incidents
We are thinking of adding Incident management to our processes. How should we go about it?
- Sun Oct 15, 2023 8:21 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: How to Enable Incidents
- Replies: 1
- Views: 15005
How to Enable Incidents
We just purchased RiskyProject Enterprise and noticed that there is Incident management in the Help. However, we have not been able to find it. Is this a separate module that we need to purchase, if not is can we enable somehow?
- Sun Oct 15, 2023 8:20 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Incidents vs Issues
- Replies: 1
- Views: 15957
Incidents vs Issues
I have been reading through your documentation and see that there are both issues and incidents referenced, and both are indicators that a risk has occurred. What is the difference between the two?
- Mon Aug 07, 2023 12:25 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Project Control in RiskyProject
- Replies: 1
- Views: 14550
Project Control in RiskyProject
We usually update information about project performance by different teams or users in Microsoft Project as part of our project control procedure. Is it possible to use this information to recalculate the chance that project will be completed on time and on budget in RiskyProject?
- Mon Jul 03, 2023 10:02 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: License Activation Already Activated Message
- Replies: 1
- Views: 15420
License Activation Already Activated Message
I am getting a license wizard pop up every time I try to use Risky Project. Then I get an error that says this License is already activated, please contact intaver institute for more information. Please advise.
- Mon Jul 03, 2023 10:02 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Viewing or Converting Labour Days to Calendar Days
- Replies: 1
- Views: 16157
Viewing or Converting Labour Days to Calendar Days
I have a chronogram and by default RiskyProject by default uses labour days for base duration. I would to show the calendar days. ¿How is it possible to get that?
- Sat Oct 08, 2022 8:14 pm
- Forum: Project Portfolio Risk Management
- Topic: Sorting and Filtering columns
- Replies: 1
- Views: 25274
Sorting and Filtering columns
I am using a trial version of RiskyProject for doing a risk analysis on a project. I am trying to sort activities by activity codes to assign duration uncertainties but do not see any option to do so in the software. I tried to look for tutorial videos on your website but there is nothing that talks...
- Fri Jun 17, 2022 12:30 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Split Tasks
- Replies: 3
- Views: 40625
Re: Split Tasks
Also duration and work of split task after import to RiskyProject can be incompatible with duration and work in Microsoft Project and other project management software. However Start and Finish Times of all tasks should be the same.
- Tue May 17, 2022 11:23 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Customizing Uncertainty Bands
- Replies: 1
- Views: 24352
Customizing Uncertainty Bands
Just downloaded your software and noticed that when I select a task or tasks and right-click to bring up the context menu, a Duration Bands menu appears that appears to calculate duration ranges based on the coefficients. Is it possible to modify these bands and where can I do this?
- Sun Jun 06, 2021 12:47 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Accessing raw cost simulation data
- Replies: 1
- Views: 24584
Accessing raw cost simulation data
Where I can go to see the calculations behind the “Cost Score” on the “Project Information window”? The cost score I’m getting is twice what the duration score is, which doesn’t make much sense to me, given that the overwhelming driver of cost in my project is labor, and the only uncertainties I hav...
- Sat Sep 19, 2020 12:20 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Task Icons
- Replies: 3
- Views: 38911
Re: Task Icons
Is any way to disable task icons?