Search found 847 matches

by Intaver Support
Sun Dec 08, 2019 3:41 pm
Forum: Project Portfolio Risk Management
Topic: Importing Risks from Excel
Replies: 3
Views: 733

Re: Importing Risks from Excel

Yes. Importing risks from Excel work the same way in RiskyProject Enterprise and RiskyProject not connected to the database. The only difference the imported risks will be saved in ALM file, not in database.
by Intaver Support
Mon Dec 02, 2019 3:40 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Managing LOE Tasks
Replies: 1
Views: 53

Re: Managing LOE Tasks

For LOE activities, it only matters if you are running resource loaded to calculate costs. If this is the case, you need to run two simulations: the first to assess the overall duration uncertainty covered by the LOE activity, the second to apply this uncertainty to the LOE task. For example, to cal...
by Intaver Support
Sat Nov 30, 2019 5:06 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Spikes appearing in histograms
Replies: 1
Views: 54

Re: Spikes appearing in histograms

In the example you are talking about, you will see spikes in the results. It is a common and expected results when analyzing using risk events. Let’s take a look at a very simple example of a 5 day activity. Now, we add 1 risk assignment: 50% chance, 50% relative delay. http://www.intaver.com/images...
by Intaver Support
Tue Nov 12, 2019 11:42 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Split Tasks
Replies: 2
Views: 2104

Re: Split Tasks

In general we don't recommend to use split task for probabilistic calculation, because uncertainties can be related to shifts and non-working time. It is hard to model and can cause confusions. Instead we recommend to use multiple tasks.
by Intaver Support
Tue Nov 12, 2019 11:36 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject Dashboards
Replies: 2
Views: 2575

Re: RiskyProject Dashboards

In RiskyProject 7.1 you can create any view of risk register with any sets of columns and filters. They are essentially dashboards. To create extra view use tabs at the bottom of risk register view.

Image
by Intaver Support
Tue Nov 12, 2019 11:30 am
Forum: Project Portfolio Risk Management
Topic: Analyzing mega schedules
Replies: 0
Views: 973

Analyzing mega schedules

What are the options for running extremely large program schedules? Our first recommendation would be to question if this is both desirable and feasible. Running simulations of extremely large schedules often generates a lot of “noise”. For example, it is almost impossible to run reliable sensitivit...
by Intaver Support
Sun Oct 27, 2019 10:39 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Using Schedule Diagnostics
Replies: 1
Views: 610

Save Results of schedule diagnostics.

Saving of the results is limited to copy and paste. The Schedule Diagnostics dialog box supports standard windows Copy and Paste functionality in the Issues in Tasks and DCMA 14pt schedule inspection panes. Right-click on any item and choose Copy from the shortcut menu To copy multiple items press a...
by Intaver Support
Sun Oct 27, 2019 10:36 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Using Schedule Diagnostics
Replies: 1
Views: 610

Using Schedule Diagnostics

The latest versions of RiskyProject include a schedule diagnostics capability based on the DCMA 14 pt analysis. To run the schedule diagnostics, on the ribbon click the Schedule tab > Schedule Diagnostics. The diagnostics will run and results are presented. Click on a test in the DCMA 14pt schedule ...
by Intaver Support
Sun Oct 27, 2019 10:31 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject Version 7.1 is released
Replies: 0
Views: 1103

RiskyProject Version 7.1 is released

RiskyProject 7.1 is releaed. Here are the new Features of RiskyProject 7.1: 1. Import Schedules from Oracle Primavera XER file : read schedules from Oracle Primavera saved in XER format. Previous versions of RiskyProject were limited to opening P6 schedules that were in MS Project XML or MPX formats...
by Intaver Support
Sun Oct 06, 2019 7:59 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Using the risk matrix to add risk in the form of a percentage of probability of a schedule delay (or cost increase)
Replies: 1
Views: 676

Re: Using the risk matrix to add risk in the form of a percentage of probability of a schedule delay (or cost increase)

The software supports both uncertainty (aleatory risk) and events (epistemic risks). Risk events are managed in the Risk workflow and can be assigned with probability and impacts to cost and schedule (fixed or relative). We recommend the use of statistical distributions to model ranges of impacts. W...
by Intaver Support
Sun Oct 06, 2019 7:49 pm
Forum: Project Portfolio Risk Management
Topic: Modeling impact of weather related events when a weather calendar is not appropriate
Replies: 1
Views: 616

Re: Modeling impact of weather related events when a weather calendar is not appropriate

Risk assignments are calculated for each activity or resource independently and it is possible to have different probabilities and outcomes for different assignments for the same risk. So you can have the same risk “Weather”, but assign different probability and impacts to different activities based...
by Intaver Support
Sun Oct 06, 2019 7:47 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: How does RiskyProject deal with risk probability when it is entered an index range vs %
Replies: 1
Views: 873

Re: How does RiskyProject deal with risk probability when it is entered an index range vs %

For quantitative analysis, we recommend adding probability as a “% “ as it is more accurate. Otherwise, if you use ranges or labels, it takes the middle value of the range for the analysis. For example, if you are using (1,2,3,4,5) as defined in the default matrix, each range represents 20% probabil...
by Intaver Support
Thu Aug 29, 2019 3:49 pm
Forum: Project Portfolio Risk Management
Topic: Linking summary tasks
Replies: 1
Views: 1273

Re: Linking summary tasks

While we do “allow” users to link summary tasks to the precedent network, it is not recommended as a best practice. It can cause logic errors, circular paths, and also issues with critical path and sensitivity analyses. Here is a well designed video that explains why you should not link summary task...
by Intaver Support
Thu Aug 29, 2019 3:47 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calculating work with resource calendars
Replies: 1
Views: 1339

Re: Calculating work with resource calendars

Work calculation occurs anytime you change the duration of a task that includes resources with resource calendars that are different from the project calendar that the tasks is using. This is due to how task duration, work, and units are calculated. When you create tasks, you must select a task type...
by Intaver Support
Thu Aug 29, 2019 3:43 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Non Working days and Time Dependent Costs
Replies: 1
Views: 1257

Re: Non Working days and Time Dependent Costs

The answer to your question depends upon they type of project you are modeling. Non-working times that include exceptions as well as periods where work cannot be performed due to weather conditions, do not calculate work for affected resources. However, in some projects, weather delays (non-working ...