Search found 798 matches

by Intaver Support
Tue Dec 11, 2018 2:15 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Reference Class estimating
Replies: 1
Views: 4

Re: Reference Class estimating

Reference class estimating, also called reference class forecasting, is a method that uses the data from previous similar project or tasks to establish a probability distribution that can be the basis for forecasting he planned activities or project. The use of this historical data provides strong e...
by Intaver Support
Tue Dec 11, 2018 2:13 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Cost Type Resources
Replies: 1
Views: 3

Re: Cost Type Resources

Cost Type resources are a method of entering costs that are not calculated as a using a rate * work formula. They can be capital or operation expenditures such as shipping or travel. They are more flexible than fixed costs as you can add multiple cost type resources to the same activity. http://www....
by Intaver Support
Tue Dec 11, 2018 2:08 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default constraint type
Replies: 1
Views: 4

Re: Default constraint type

In RiskyProject you cannot set a default setting for the constraint typ. In RiskyProject, when you add a new task the constraint type will always default to As Soon as Possible. The reason for this is that in schedule risk analysis hard constraints of any kind should be used as this will prevent the...
by Intaver Support
Sun Nov 18, 2018 12:54 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Defining Uncertainty for Lags
Replies: 1
Views: 310

Re: Defining Uncertainty for Lags

The Predecessor tab, which is located in the Task Information dialog box, is the central view for defining task predecessors. As well as defining predecessor link (Task ID, Name, and Type) you can also define the lag between the predecessor and successor as a 3pt uncertainty. To add the uncertainty ...
by Intaver Support
Sun Nov 18, 2018 12:47 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Irreducible Risk
Replies: 1
Views: 305

Re: Irreducible Risk

Irreducible risk is sum of the aleatory risk, which is modeled using 3 point estimates for Low, Most Likely, and High for duration and cost, and residual risk that remain due to risk events or epistemic risks that cannot be completely eliminated. Often irreducible and residual risk are considered eq...
by Intaver Support
Sun Nov 18, 2018 12:43 pm
Forum: Project Portfolio Risk Management
Topic: Increasing performance for simulations on large schedules
Replies: 1
Views: 315

Re: Increasing performance for simulations on large schedules

With extremely large projects (>50,000) running simulations can be an arduous task. Just loading data into applications can take hours and is one of the reasons that it is not a recommended practice. However, some mega projects require this analysis as part of their Integrated Program Management (IP...
by Intaver Support
Sun Nov 04, 2018 11:37 am
Forum: Project Portfolio Risk Management
Topic: Exporting XML to MS Project
Replies: 1
Views: 389

Re: Exporting XML to MS Project

This depends on the objectives for running the analysis? There are a few issues with exporting the results back to MSP that you need to consider: 1. When you open the xml file, if you try import into an existing file, it could overwrite data not directly associated with the simulation results such a...
by Intaver Support
Sun Nov 04, 2018 11:35 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Using percentiles to calculate management baselines
Replies: 1
Views: 425

Re: Using percentiles to calculate management baselines

If you want to use the results of the simulation to create a risk adjusted baseline that the percentile that you use is really a judgement call. Typically, customers who do use the feature export out the Base results (the average durations for each task) to xml which can then be imported into schedu...
by Intaver Support
Sun Nov 04, 2018 11:30 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calculating Schedule Margin
Replies: 1
Views: 563

Re: Calculating Schedule Margin

Schedule margin normally refers to tasks that are not related to delivering project scope that are added to the project to account for unmanaged risk and uncertainty and increase the chance that the project will be delivered on time. Required schedule margin can be calculated as part of your Monte C...
by Intaver Support
Thu Oct 25, 2018 11:27 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Show Risk IDs
Replies: 1
Views: 288

Re: Show Risk IDs

Risk IDs are a hard coded property of the risk register and differ from the row number that is shown on the far left of the risk register. By default or “Out of the Box”, the Risk ID is not shown in the Risk Register. To add the Risk ID, right-click on a column header in the Risk Register where you ...
by Intaver Support
Mon Oct 15, 2018 10:49 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default Settings for Risk Assignments
Replies: 1
Views: 347

Re: Default Settings for Risk Assignments

Default settings for risk assignment can be set in the Project Options > Risk tab. While it may seem somewhat odd that there would be default settings as each risk should have its own inherent probability and impacts, default settings are actually designed to show new users how risks assignments (ch...
by Intaver Support
Mon Oct 15, 2018 10:47 am
Forum: Project Portfolio Risk Management
Topic: Generating Risk IDS automatically
Replies: 1
Views: 311

Re: Generating Risk IDS automatically

The “Generate Risk IDs automatically” option is located in the Project > Risk tab. As a general rule, we recommend that you generate your risk IDs automatically as the automation ensures that risk IDs created both automatically and consistently and minimizes user error or inadvertent replication. In...
by Intaver Support
Mon Oct 15, 2018 10:44 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Hard vs soft constraints
Replies: 3
Views: 1179

Re: Hard vs soft constraints

Please be very careful with relaxing some constraints during import files from other scheduling software because it may cause incompatibility between schedules in RiskyProject and other scheduling software.
by Intaver Support
Mon Oct 15, 2018 10:42 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Differences between resource types
Replies: 2
Views: 515

Re: Differences between resource types

Generally different resource types in RiskyProject software are implemented similarly to Microsoft Project. It provides very good compatibility between Microsoft Project and RiskyProject. Other project scheduling software may implement resource types differently, however we are trying to ensure good...
by Intaver Support
Mon Oct 15, 2018 10:39 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Correlating risk assignments option
Replies: 1
Views: 296

Re: Correlating risk assignments option

The “ Risk assignments to different tasks are correlated option” is located in the Project > Risk tab. So how does it work and why should you use it? Risks can be assigned to one or more tasks and resources. In the underlying risk model, each assignment is considered its own risk event. When the ris...

Go to advanced search