They can do this in the Default Properties view selecting all of the properties, and copy using the shortcut menu. This list can then by pasted into a spreadsheet or document for review.
Search found 992 matches
- Wed Mar 20, 2024 10:14 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Copying the Default Risk Properties for Review
- Replies: 1
- Views: 43
- Wed Mar 20, 2024 10:10 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Low number of Sensitivity Results
- Replies: 1
- Views: 46
Re: Low number of Sensitivity Results
Best Practice: Setting Sensitivity Coefficient Threshold There is a threshold that can be set for viewing sensitivity results, where any results that do not meet the sensitivity coefficient threshold are not show as way to simplify the analysis of schedules. If you many activities with similar level...
- Wed Mar 20, 2024 10:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Sorting Risk Assignments view
- Replies: 1
- Views: 52
Re: Sorting Risk Assignments view
The Risk Assignment view doesn't sort and the Risk ID is not one of the data fields available. The Assignment view is listed alphabetically. But the Risk Register you can list Alphabetically as well using the buttons at the top left of the Register view so that they are listed in the same order as R...
- Fri Feb 09, 2024 11:03 pm
- Forum: Project Portfolio Risk Management
- Topic: Where is the End User License Agreement
- Replies: 1
- Views: 392
Re: Where is the End User License Agreement
We do include the EULA as part of the installation Wizard, which must be accepted prior to installation of the software. An example is shown below. https://www.intaver.com/images/RP_Forum_EULA.png It is also available as part of the installation package. You can also request a copy of the current EU...
- Fri Feb 09, 2024 10:58 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Low number of iterations
- Replies: 1
- Views: 389
Re: Low number of iterations
The number of iterations that will be run is set in the Project Options > Calculations tab. Based on the number of iterations you are seeing, convergence is enabled. Convergence occurs when the simulation results equal the mean and standard deviation values that are defined. To run a higher number o...
- Fri Feb 09, 2024 10:55 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Updating file causing short delays
- Replies: 1
- Views: 380
Re: Updating file causing short delays
RiskyProject has 2 default calculation settings: Deterministic and Probabilistic. When Probabilistic is selected, RiskyProject has an algorithm in which it monitors the size of the data and available computer resources and if it calculates that it can run it in one second it will run a simulation. I...
- Thu Jan 11, 2024 6:45 pm
- Forum: Project Portfolio Risk Management
- Topic: Setting the height of rows
- Replies: 1
- Views: 1257
Re: Setting the height of rows
Our current Risk Register does not support wrapping text.
Normally the extra width is due to non-breaking spaces or other formatting in the Excel. To resize, hover over the row border and left-click which will change to cursor so that you can drag the row border to the width you require.
Normally the extra width is due to non-breaking spaces or other formatting in the Excel. To resize, hover over the row border and left-click which will change to cursor so that you can drag the row border to the width you require.
- Thu Jan 11, 2024 6:43 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Legacy MSP xml format error message
- Replies: 1
- Views: 1092
Re: Legacy MSP xml format error message
You probably see the following message: https://www.intaver.com/images/RP_Forum_XMLMSG.png As of 2019, the xml generated by earlier versions of MSP and RiskyProject are considered “Legacy” formats, which can cause these types of errors, though they do not happen consistently. To allow the use of old...
- Thu Jan 11, 2024 6:39 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Maximum number of named users for RiskyProject Professional cannot be greater than error
- Replies: 1
- Views: 1305
Re: Maximum number of named users for RiskyProject Professional cannot be greater than error
With the release of version 7.2 the license now includes a designation for the number of named users for each license type that were purchased as part of the commercial contract. For example, if you purchased 5 Professional and 10 Risk Register clients for a total of 15 named users. In the User Mana...
- Sat Dec 16, 2023 1:18 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Enterprise License expired
- Replies: 1
- Views: 1724
Re: Enterprise License expired
Hello, unlike the desktop version, the Enterprise license is not perpetual and can expire. The license expiry duration and dates can be viewed in the User Management > License and Security tab. Typically, a purchased license has a default of duration of 10000 days, but in cases of pilot or evaluatio...
- Fri Dec 15, 2023 9:19 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Inserting new columns to the Risk Register
- Replies: 1
- Views: 2911
Re: Inserting new columns to the Risk Register
Yes. You can insert any custom columns to the Risk Register. The number of such columns is essentially unlimited. It is a two step process: 1. Insert new risk property to the Risk Register. To do it just go to Risk -> Default Risk Properties. and insert any new property. https://www.intaver.com/imag...
- Fri Dec 15, 2023 9:09 pm
- Forum: Project Portfolio Risk Management
- Topic: Incorrect username or password error message logging onto database
- Replies: 1
- Views: 1719
Re: Incorrect username or password error message logging onto database
The problem most likely is being caused with the authentication method that was selected when initially setting up the user management and authentication method. Both of the issues have the same root cause. The ability for users not defined in the RiskyProject user management to login indicates that...
- Sun Oct 15, 2023 8:32 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Incidents vs Issues
- Replies: 1
- Views: 2966
Re: Incidents vs Issues
Incidents and issues are interrelated but are used differently within RiskyProject to analyze and manage risks through the risk lifecycle. Issues are part of the Risk Lifecycle on how risks should be managed. In Risk Lifecycle risks can go through three phases: Risks, Issues, and Lessons Learned. In...
- Sun Oct 15, 2023 8:29 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: How to Enable Incidents
- Replies: 1
- Views: 1924
Re: How to Enable Incidents
Answer Incident management is included with RiskyProject Enterprise and is not part of the Professional desktop version. To enable Incidents: 1. On the Projects tab, click Portfolio Options > General tab. 2. Click Enable incident tracking and reporting (Incident tab). 3. Click OK. Incidents are now ...
- Sun Oct 15, 2023 8:26 pm
- Forum: Project Portfolio Risk Management
- Topic: Adding Incidents
- Replies: 1
- Views: 1843
Re: Adding Incidents
This is a bigger topic than a single forum post can support, but it can be broken down into several steps. 1. Enable the Incident Management in RiskyProject Professional Enterprise desktop top client. 2. Setup the Incident Register. This is done in the Incidents tab > Settings group. https://www.int...