Search found 4 matches

by RKL
Tue Apr 17, 2012 12:46 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Matrix - More than 3 colour bands possible?
Replies: 1
Views: 13116

Risk Matrix - More than 3 colour bands possible?

My organization uses a 5x5 Matrix with 5 Levels of risk as their common reporting policy: For Threats: Low Threat - Green Medium Threat - Yellow Significant Threat - Orange High Threat - Red Very High Threat - Bright Red For Opportunities (still in development) - They use the same designators (Low t...
by RKL
Fri Mar 13, 2009 8:32 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Duration convergence affecting Cost Validity?
Replies: 1
Views: 15156

Duration convergence affecting Cost Validity?

If I am interested in only doing a simple model of Cost Impacts and use a single task with all cost risks assigned to it, would the solution for the Cost Risk be invalid since the convergence is based on duration? Would it be better to: Use a single task with an extremely wide range of duration with...
by RKL
Wed Nov 23, 2005 1:41 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Drop Down Calendar Incorrect
Replies: 2
Views: 20503

I can't get it again either.

I suspect the problem was "Me". I may have incorrectly selected the wrong Nov 11th in some other year.

BTW, really surprised how big your calendar is. Ranging from Jan 1950 to Dec 2080 seems a bit of overkill <grin>

Feel free to kill this entire thread

Cheers

RKL
by RKL
Tue Nov 22, 2005 1:10 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Drop Down Calendar Incorrect
Replies: 2
Views: 20503

Drop Down Calendar Incorrect

While entering a constrained date in the Task Information Panel, I used the Calendar Selection.

The Calendar displayed is "Off". It is showing 11 November 2005 as a Sunday when it was a Friday.

Intaver Support: Please investigate and report back.