Reporting on Sensitivity Analysis

How can I include tornado chart to report?
by BusinessDecisions
Fri Jun 09, 2017 11:21 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Simulation Results for Milestones
Replies: 1
Views: 1787

Simulation Results for Milestones

How can I see statistical distribution of finish time for milestone?
by BusinessDecisions
Tue Nov 15, 2016 2:57 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Cost type resources.
Replies: 1
Views: 2095

Cost type resources.

Does version 6.1 support cost type resources?
by BusinessDecisions
Fri Oct 21, 2016 3:40 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Customizing the Tornado Chart
Replies: 1
Views: 2501

Customizing the Tornado Chart

It seems that the Tornado Chart has different colors for different types of data and different calculations. Can you modify the colors? Also, which is the preferred “Sensitivity calculation algorithm”. Does it change the ranking at all?
by BusinessDecisions
Fri Oct 21, 2016 3:39 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calendar Exceptions
Replies: 1
Views: 1975

Calendar Exceptions

Is there any way to customize the calendars such that every 2nd Friday is a half day or similar recurring exceptions to the basic project calendar?
by BusinessDecisions
Sun Sep 20, 2015 11:00 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Difference between mitigation and response plans
Replies: 1
Views: 3701

Difference between mitigation and response plans

What is the difference for risk mitigation and response plans in RiskyProject and how does it reflected in schedule risk analysis?
by BusinessDecisions
Sun Sep 20, 2015 10:58 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Defaults for risk mitigation and response plans
Replies: 1
Views: 2438

Defaults for risk mitigation and response plans

Every time I add a mitigation activity to the waterfall chart, it seems to automatically decrease the impact by 5% which I don’t want. It looks like a default but I don’t see any setting in the options.
by BusinessDecisions
Mon Apr 09, 2007 11:39 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: MPX Export to MS Project 2007
Replies: 2
Views: 11633

Do you include any other features to RP 2.1?
by BusinessDecisions
Tue Apr 03, 2007 12:36 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: MPX Export to MS Project 2007
Replies: 2
Views: 11633

MPX Export to MS Project 2007

I'm trying to import MPX file created in RiskyProject into MS Project 2007. Apparently there is problem here. First of all MPX file is considered to be a legacy feature in MS Project 2007. I had to enable it in Tool -> Options. But even after that MPX could not be properly read in MS Project 2007. D...