Search found 11 matches

by MTC465
Fri Sep 21, 2018 1:21 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Displaying Project Name in Project Summary
Replies: 1
Views: 16873

Displaying Project Name in Project Summary

We created a trial Risk Register in another similar project schedule (older dated timeline). Is there a way to reset the Project Name that would replace these older project labels?
by MTC465
Fri Sep 21, 2018 1:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: What is Stat Fit?
Replies: 1
Views: 13943

What is Stat Fit?

We have seen message “You do not have “Stat Fit”. What does Stay Fit do?
by MTC465
Fri Sep 21, 2018 1:19 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Outliers in Result Views
Replies: 2
Views: 21676

Outliers in Result Views

In the Project Summary view, we have “Outlier(s)” that are skewing the Y Axis. What is the best way to find the source of the Outliers so that we can tweak or correct them and see a realistic distribution pattern?
by MTC465
Fri Mar 10, 2017 8:47 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Maximum number of mitigation and response plans
Replies: 1
Views: 11434

Maximum number of mitigation and response plans

What is the maximum number of mitigation and response plans in RiskyProject?
by MTC465
Tue Dec 15, 2015 1:36 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Question about the Addin simulations with incomplete data
Replies: 1
Views: 12765

Question about the Addin simulations with incomplete data

One of users had incorrectly added information required for selecting the statistical distribution as show in the Mapping dialog. He was just entering in a text description “triangular” in the field he had mapped, in this case Text 27. From the documentation it appears that we need to use the Durati...
by MTC465
Tue Dec 15, 2015 1:33 pm
Forum: Project Portfolio Risk Management
Topic: How do I add the Risk Matrix to a report.
Replies: 1
Views: 9205

How do I add the Risk Matrix to a report.

As part of our project risk reporting we would like to include the Risk Matrix, is there any way to add this to the Risk Register report for the project portfolio?
by MTC465
Wed Dec 09, 2015 4:14 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Monte Carlo simulation results for tasks
Replies: 1
Views: 12660

Monte Carlo simulation results for tasks

Have you thought of any easier method to bring up the task charts? Once we have run the simulations, it would be nice just to select a task and bring up the results. Now it takes a couple of extra clicks, which seems unnecessary.
by MTC465
Wed Dec 09, 2015 4:09 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Risk arrows on the Gantt Chart
Replies: 1
Views: 10840

Risk arrows on the Gantt Chart

We have found that showing the location of the risks on the Gantt chart is very useful during our project reviews. Are you considering anyway show details of the risk without having to leave the Gantt chart. We think that this type of interaction would be very useful.
by MTC465
Wed Sep 02, 2015 9:56 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Relative vs. fixed (absolute) delays for project risks
Replies: 1
Views: 9358

Relative vs. fixed (absolute) delays for project risks

When you are adding risks, their is a choice between fixed (absolute) durations in days or relative delays. When should you use fixed rather than relative outcomes?
by MTC465
Fri Dec 08, 2006 2:58 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Event Chain Methodology and Monte Carlo Simulations
Replies: 3
Views: 24040

Can I define a statistical distribution for duration? For example normal distribution, mean 5, standard deviation 0.75?
by MTC465
Fri Dec 08, 2006 2:56 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Early Start, Early Finish, Late Start, Late Finish
Replies: 1
Views: 18294

Early Start, Early Finish, Late Start, Late Finish

I'd like to see Early Start, Early Finish, Late Start, Late Finish fields. Do you have in Lite or Professional versions?