Search found 826 matches

by Intaver Support
Thu Mar 14, 2019 1:57 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying most likely values in the Task Information > Distribution dialog box.
Replies: 3
Views: 438

Re: Modifying most likely values in the Task Information > Distribution dialog box.

The Distribution tab in the Task Information dialog box allows you to fine-tune the meaning of the low and high estimates in terms of percentiles or the standard deviation coefficient. This means that you are setting the probability boundaries for the distribution. In effect this means that you excl...
by Intaver Support
Thu Mar 14, 2019 1:52 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying most likely values in the Task Information > Distribution dialog box.
Replies: 3
Views: 438

Re: Modifying most likely values in the Task Information > Distribution dialog box.

When you assign a statistical distribution to an activity that has best case, most likely, and worst case estimates, the software calculates the probability distribution function based on the estimates and the statistical distribution type. The Distribution tab in the Task Information dialog box all...
by Intaver Support
Thu Mar 14, 2019 1:47 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Automatically update Opportunity Matrix
Replies: 1
Views: 430

Re: Automatically update Opportunity Matrix

If you use the Risk Tolerance slider to modify the threat risk matrix, the opportunities matrix will update accordingly. http://www.intaver.com/images/RP_Forum_ToleranceOp.png However if you modify the default color schemes in either the Threat or Opportunity matrix (see the topic “Probability and i...
by Intaver Support
Tue Feb 19, 2019 10:23 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default Task Types
Replies: 4
Views: 1057

Re: Default Task Types

Fixed Units is probably the best task type for schedule risk analysis because of the manner in how task types are used to recalculate Work, Units, or Duration. In Monte Carlo simulations, we are measuring how changes to task durations can not only affect project duration and finish time, but also ho...
by Intaver Support
Wed Feb 06, 2019 3:18 pm
Forum: Project Portfolio Risk Management
Topic: Assigning risks to Agile projects
Replies: 1
Views: 529

Re: Assigning risks to Agile projects

In Agile, risks as understood in more traditional risk analysis don’t exist or more specifically, they are not managed as risk events, but rather issues that could impact the progress of specific sprints in the delivery of a storyboard. Issues are conditions that have 100% probability of happening, ...
by Intaver Support
Wed Feb 06, 2019 3:11 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk Scoring Options
Replies: 1
Views: 582

Re: Risk Scoring Options

This answer will focus on the two risk scoring methods available in the Format Risk > Advanced Settings dialog pictured below. http://www.intaver.com/images/RP_Forum_ScoringMethod.png The two risk scoring methods are: Method 1 - Combined impact: maximum impact of all categories, and Method 2 - Combi...
by Intaver Support
Wed Feb 06, 2019 3:06 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Default Task Types
Replies: 4
Views: 1057

Re: Default Task Types

Yes. In the Project Options > Duration tab you an set the default Task Type. If you do not manually change this default setting, the Task Type is set to Fixed Units.

Image
by Intaver Support
Fri Jan 11, 2019 2:32 pm
Forum: Project Portfolio Risk Management
Topic: Impact of estimate quality on risk assessments
Replies: 1
Views: 470

Re: Impact of estimate quality on risk assessments

In of themselves, the quality or accuracy of your cost and schedule estimates are a major risk a does not matter whether you are performing Monte Carlo or Critical Path analysis. The quality of any analysis is dependent upon the quality or accuracy of the inputs or as more commonly known Garbage In ...
by Intaver Support
Fri Jan 11, 2019 2:24 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Agile and schedule risk analysis
Replies: 1
Views: 580

Re: Agile and schedule risk analysis

1. It is possible to model Agile projects in RiskyProject, however it does take some adjustment in the methodology and process. 2. Agile has iterations and storyboards which represent the steps (iterations) and deliverables (storyboards) 3. In RiskyProject you can model iterations as activities. Sto...
by Intaver Support
Fri Jan 11, 2019 2:19 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Opportunity Risk Matrix
Replies: 5
Views: 3541

Re: Opportunity Risk Matrix

Here are a couple of trends that we have seen emerge over the past years that are becoming more popular. Black Swan Risk In this case, the default risk matrix setting is used, but the Critical risk cells are extended down to the bottom right corner of the matrix. This is done so that any risks that ...
by Intaver Support
Wed Dec 26, 2018 1:08 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Opportunity Risk Matrix
Replies: 5
Views: 3541

Re: Opportunity Risk Matrix

There are no limits to the number of colors or the range of colors that you can apply to the risk matrix. As an example, if you had a standard 5x5 matrix with 25 cells, you could have 25 different colors. We don’t recommend this, but it is becoming very common to see risk matrixes with up to 6 color...
by Intaver Support
Wed Dec 26, 2018 1:01 pm
Forum: Project Portfolio Risk Management
Topic: Customized risk matrix settings for different users
Replies: 3
Views: 2317

Re: Customized risk matrix settings for different users

The Risk Trends reports can be modified using the Risk Trend Chart Settings in the Format Risk Matrix dialog box. By default, the Risk Trends provides the number of risks in each risk severity category over a designated number of periods. The periods can be set using the Risk Trend Chart periodicity...
by Intaver Support
Wed Dec 26, 2018 12:55 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying Risk Matrix colors
Replies: 3
Views: 1861

Re: Modifying Risk Matrix colors

The Risk Matrix Reports are the Risk Matrix, Risk History, Risk Trends, and Risk Monitor. All are providing slightly different information on both historical and current assessment of your project risks. The Risk Matrix report allows you to show the original and post mitigated assessments for each r...
by Intaver Support
Tue Dec 11, 2018 2:15 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Reference Class estimating
Replies: 1
Views: 1154

Re: Reference Class estimating

Reference class estimating, also called reference class forecasting, is a method that uses the data from previous similar project or tasks to establish a probability distribution that can be the basis for forecasting he planned activities or project. The use of this historical data provides strong e...
by Intaver Support
Tue Dec 11, 2018 2:13 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Cost Type Resources
Replies: 1
Views: 1174

Re: Cost Type Resources

Cost Type resources are a method of entering costs that are not calculated as a using a rate * work formula. They can be capital or operation expenditures such as shipping or travel. They are more flexible than fixed costs as you can add multiple cost type resources to the same activity. http://www....