Search found 856 matches

by Intaver Support
Sun Oct 27, 2019 10:39 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Using Schedule Diagnostics
Replies: 1
Views: 1391

Save Results of schedule diagnostics.

Saving of the results is limited to copy and paste. The Schedule Diagnostics dialog box supports standard windows Copy and Paste functionality in the Issues in Tasks and DCMA 14pt schedule inspection panes. Right-click on any item and choose Copy from the shortcut menu To copy multiple items press a...
by Intaver Support
Sun Oct 27, 2019 10:36 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Using Schedule Diagnostics
Replies: 1
Views: 1391

Using Schedule Diagnostics

The latest versions of RiskyProject include a schedule diagnostics capability based on the DCMA 14 pt analysis. To run the schedule diagnostics, on the ribbon click the Schedule tab > Schedule Diagnostics. The diagnostics will run and results are presented. Click on a test in the DCMA 14pt schedule ...
by Intaver Support
Sun Oct 27, 2019 10:31 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject Version 7.1 is released
Replies: 0
Views: 2188

RiskyProject Version 7.1 is released

RiskyProject 7.1 is releaed. Here are the new Features of RiskyProject 7.1: 1. Import Schedules from Oracle Primavera XER file : read schedules from Oracle Primavera saved in XER format. Previous versions of RiskyProject were limited to opening P6 schedules that were in MS Project XML or MPX formats...
by Intaver Support
Sun Oct 06, 2019 7:59 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Using the risk matrix to add risk in the form of a percentage of probability of a schedule delay (or cost increase)
Replies: 1
Views: 1311

Re: Using the risk matrix to add risk in the form of a percentage of probability of a schedule delay (or cost increase)

The software supports both uncertainty (aleatory risk) and events (epistemic risks). Risk events are managed in the Risk workflow and can be assigned with probability and impacts to cost and schedule (fixed or relative). We recommend the use of statistical distributions to model ranges of impacts. W...
by Intaver Support
Sun Oct 06, 2019 7:49 pm
Forum: Project Portfolio Risk Management
Topic: Modeling impact of weather related events when a weather calendar is not appropriate
Replies: 1
Views: 1253

Re: Modeling impact of weather related events when a weather calendar is not appropriate

Risk assignments are calculated for each activity or resource independently and it is possible to have different probabilities and outcomes for different assignments for the same risk. So you can have the same risk “Weather”, but assign different probability and impacts to different activities based...
by Intaver Support
Sun Oct 06, 2019 7:47 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: How does RiskyProject deal with risk probability when it is entered an index range vs %
Replies: 1
Views: 1482

Re: How does RiskyProject deal with risk probability when it is entered an index range vs %

For quantitative analysis, we recommend adding probability as a “% “ as it is more accurate. Otherwise, if you use ranges or labels, it takes the middle value of the range for the analysis. For example, if you are using (1,2,3,4,5) as defined in the default matrix, each range represents 20% probabil...
by Intaver Support
Thu Aug 29, 2019 3:49 pm
Forum: Project Portfolio Risk Management
Topic: Linking summary tasks
Replies: 1
Views: 1685

Re: Linking summary tasks

While we do “allow” users to link summary tasks to the precedent network, it is not recommended as a best practice. It can cause logic errors, circular paths, and also issues with critical path and sensitivity analyses. Here is a well designed video that explains why you should not link summary task...
by Intaver Support
Thu Aug 29, 2019 3:47 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Calculating work with resource calendars
Replies: 1
Views: 1752

Re: Calculating work with resource calendars

Work calculation occurs anytime you change the duration of a task that includes resources with resource calendars that are different from the project calendar that the tasks is using. This is due to how task duration, work, and units are calculated. When you create tasks, you must select a task type...
by Intaver Support
Thu Aug 29, 2019 3:43 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Non Working days and Time Dependent Costs
Replies: 1
Views: 1676

Re: Non Working days and Time Dependent Costs

The answer to your question depends upon they type of project you are modeling. Non-working times that include exceptions as well as periods where work cannot be performed due to weather conditions, do not calculate work for affected resources. However, in some projects, weather delays (non-working ...
by Intaver Support
Wed Aug 07, 2019 11:18 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Using weather calendar vs risk events for cost analysis
Replies: 1
Views: 1371

Re: Using weather calendar vs risk events for cost analysis

Weather calendars are specifically designed to model known ranges of weather-related non-working days during the execution of a project. The main effect of using weather calendars when also performing cost analysis of time dependent cost analysis using resource rates is that even though there is a w...
by Intaver Support
Wed Aug 07, 2019 11:17 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Task Icons
Replies: 1
Views: 1355

Re: Task Icons

Tasks can be identified with 6 different icons: summary tasks, summary tasks with constraints, subtasks, subtasks with constraints, subtask with notes, and subtasks with notes and constraints. These icons definitions can be viewed in the Legends pane, which can be enabled in the Tools tab, View grou...
by Intaver Support
Wed Aug 07, 2019 11:13 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculating Cost Contingency
Replies: 1
Views: 1832

Re: Calculating Cost Contingency

In our methodology, cost contingency is calculated as the difference between the base estimate and a calculated percentile that is calculated from the simulation. This is referred to as “risk adjusted” cost contigency. A very common value used is P80 which means that 8 out of 10 times the cost of th...
by Intaver Support
Tue Jul 23, 2019 4:50 pm
Forum: Project Portfolio Risk Management
Topic: Sorting Risk Register
Replies: 3
Views: 3279

Re: Sorting Risk Register

In new RiskyProject 7.1 which suppose to be released very shortly we significantly improved sorting capabilities.
by Intaver Support
Tue Jul 23, 2019 4:47 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Importing Risk Templates to Risk Registers
Replies: 1
Views: 1186

Re: Importing Risk Templates to Risk Registers

Yes you can, but a risk template will overwrite all information in a risk register. Therefore, it is better to think of how risk templates differ from risk registers. Risk templates are lists of risks with risk assignments. Assignments are composed of Type, Chance, Outcome Type, Outcome, and statist...
by Intaver Support
Tue Jul 23, 2019 4:45 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Residual risk vs Unmanageable risk
Replies: 1
Views: 1331

Re: Residual risk vs Unmanageable risk

This is a question we do get from people who have sat in on our webinars or read some of our blog posts as they seem to describe the same thing, but they do describe slightly different types of risk. Residual risk is the risk that will still remain after risk management activities or plans have been...