Search found 1031 matches
- Mon Aug 07, 2023 12:49 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Project Control in RiskyProject
- Replies: 2
- Views: 355291
Re: Project Control in RiskyProject
In RiskyProject you can perform project risk analysis on any phase of the project based on information from project control. Here is the process: 1. In Microsoft Project, Oracle Primavera or any other software where you maintain the original project schedule, you can enter information about % percen...
- Mon Aug 07, 2023 12:14 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Assigning a multiday delay to a one day task
- Replies: 1
- Views: 80522
Re: Assigning a multiday delay to a one day task
You would need to use Fixed Duration Delay (5 to 10 days) rather than Relative Delay. It is possible to model a 500% - 1000% relative delay as well.
- Mon Aug 07, 2023 12:12 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: License activation error
- Replies: 1
- Views: 83717
Re: License activation error
RiskyProject allows three activations of one license. If you are moving RiskyProject license from one computer to another and you exceed number of actication allowed, you will receive a message "License has already been activated". In this case you need to contact Intaver Institute and we ...
- Thu Jul 27, 2023 1:08 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Setting a statistical distribution for group of tasks
- Replies: 2
- Views: 109064
Re: Setting a statistical distribution for group of tasks
We recommend to use Uncertainty Bands for settings distributions for cost and duration for the group of tasks. Such approach makes setting uncertainties most consistent across the project. In case of RiskyProject Enterprise uncertainty band information is saved in RiskyProject database, which makes ...
- Thu Jul 27, 2023 1:04 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Criticality Index
- Replies: 2
- Views: 108754
Re: Criticality Index
After the column with the criticality index is inserted to the grid, the grid information will be saved in to ALM file. So when you reopen project file this column will be presented. It is also possible to save column layout for all future new projects. It is done using Schedule -> Project Options -...
- Thu Jul 27, 2023 12:58 pm
- Forum: Project Portfolio Risk Management
- Topic: Schedule Reports that show Uncertainty Bands.
- Replies: 2
- Views: 102423
Re: Schedule Reports that show Uncertainty Bands.
It is important to note that all information about Uncertainty Bands in RiskyProject Enterprise are saved into the Enterprise database. As a result the users in one organization will be able to share settings for the uncertainty bands. Only administrator are able the edit and save these settings. Th...
- Mon Jul 03, 2023 10:09 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Viewing or Converting Labour Days to Calendar Days
- Replies: 1
- Views: 90721
Re: Viewing or Converting Labour Days to Calendar Days
Calendar days are referred to as “elapsed days” or edays. Use of elapsed duration setting in the Advanced Settings in the desktop version when you import schedule from Microsoft Project. It is because the letter that is used to denote elapsed days is dependent upon the language settings. http://www....
- Mon Jul 03, 2023 10:03 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: License Activation Already Activated Message
- Replies: 1
- Views: 90267
Re: License Activation Already Activated Message
We can refresh the license, but this will continue to happen as it appears that the license information cannot be written to your computers registry. Typically this occurs when there are insufficient user permissions to write to the license information to the registry, a utility is removing "un...
- Mon Jul 03, 2023 5:49 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Pre and Post-Mitigation Simulation Results
- Replies: 1
- Views: 90102
Re: Pre and Post-Mitigation Simulation Results
The problem appears to be that you have not created a post mitigated baseline with reduced probabilities etc due to the mitigation activities. Assigning mitigation activities in the waterfall chart are only a forecast but do not impact the simulation results. To create a post mitigated baseline, you...
- Sun Apr 02, 2023 11:15 am
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Professional vs RiskyProject Enterprise
- Replies: 2
- Views: 136862
Re: RiskyProject Professional vs RiskyProject Enterprise
In addition to other features shown above RiskyProject Enterprise integrates with Proteus Envision. Please visit https://sna-software.com/proteus-envision/ for information about this product.
- Sun Apr 02, 2023 11:13 am
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Risk Outcomes vs Moment of Risk
- Replies: 2
- Views: 170359
Re: Risk Outcomes vs Moment of Risk
We did some analysis, how moment of risk affects results of Monte Carlo schedule risk analysis. We would that in some cases different settings of Moment of Risk may affect results, such as mean project duration and cost, very significantly. We recommend to carefully analyze the Moment of Risk if you...
- Sun Apr 02, 2023 11:08 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Scaling risk form
- Replies: 2
- Views: 136264
Re: Scaling risk form
This scaling is likely related to a monitor display setting. We have found with some HD displays Windows doesn't scale the application properly. In this cases it is displaying all the fields, but not scaling correctly. This is a known issue and particularly if your setup includes multiple monitors w...
- Sat Jan 07, 2023 3:27 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Import mitigation plans
- Replies: 1
- Views: 90941
Re: Import mitigation plans
Using the Import > Risks from Excel feature, you can now import mitigation plans with updates. https://www.intaver.com/images/RP_Forum_MitExcel.png Each row of such Excel file is a mitigation plan assigned to particular risk; such file must have mitigation name and associated risk as a separate colu...
- Sat Jan 07, 2023 3:22 pm
- Forum: Project Portfolio Risk Management
- Topic: Mitigation Waterfall Chart
- Replies: 1
- Views: 91147
Re: Mitigation Waterfall Chart
With the release of version 7.2, we have added significant new mitigation planning capabilities of which required the addition of an additional mitigation view as the existing views were designed to support the new capabilities. One of the main changes is the ability to track planned and actuals imp...
- Sat Jan 07, 2023 3:13 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: JCL chart
- Replies: 2
- Views: 137008
Re: JCL chart
Joint confidence level chart can be accessed from Project Summary view in the Analysis tab of Workflow menu or ribbon: https://www.intaver.com/images/RP_Forum_JCL1.png In the latest release of the software Joint confidence level chart includes frontier lines or lines with equal probabilities of cost...