Search found 823 matches

by Intaver Support
Mon Mar 05, 2018 10:01 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Maximum number of risks
Replies: 2
Views: 1297

Re: Maximum number of risks

Theoretically there is no maximum number of risks. However, the question is what value is being produced by having hundreds of risks listed in your risk register. The reason why we list them is so that they can be managed, and it is if not impossible, extremely difficult to manage hundreds of risks....
by Intaver Support
Mon Mar 05, 2018 9:56 am
Forum: Project Portfolio Risk Management
Topic: Sorting Risk Register
Replies: 2
Views: 1336

Re: Sorting Risk Register

RiskyProject’s risk register provides many options to sort a risk register based on any property including risk categories. To sort based on risk categories, you need to use the Hierarchy based on drop down list located at the top of the risk register. From the drop-down list, choose Categories. htt...
by Intaver Support
Thu Feb 22, 2018 4:01 pm
Forum: Project Portfolio Risk Management
Topic: RiskyProject Enterprise System requirements
Replies: 1
Views: 1060

Re: RiskyProject Enterprise System requirements

RiskyProject Enterprise use both a desktop client with a Windows operating system and database server. RiskyProject desktop clients will run on any Windows computer that meets the minimum requirements listed below. RiskyProject Enterprise database is relatively light weight and does not require powe...
by Intaver Support
Thu Feb 22, 2018 3:58 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Multicore processing in RiskyProject
Replies: 2
Views: 1020

Re: Multicore processing in RiskyProject

RiskyProject uses multi-core processing to calculate the iterations of the project schedules. While it does not use all the cores, it will use as many as the operating system allows it. For example, if you had a dual quad core system, typically you will see that RiskyProject will use all cores when ...
by Intaver Support
Tue Feb 13, 2018 12:53 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Probabilistic vs Weather Calendar
Replies: 3
Views: 1571

Re: Probabilistic vs Weather Calendar

Here is how you can define Probabilistic calendar in project settings.

Image
by Intaver Support
Tue Feb 13, 2018 12:51 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Probabilistic vs Weather Calendar
Replies: 3
Views: 1571

Re: Probabilistic vs Weather Calendar

You should use weather calendars when you have historical weather data, if not, or you are modeling a schedule that could shift due to non weather related causes. Weather calendars are useful when you have historical weather records that can be used to estimate the normal ranges of weather related n...
by Intaver Support
Mon Feb 05, 2018 11:04 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How do Task Types work with Monte Carlo
Replies: 1
Views: 1157

Re: How do Task Types work with Monte Carlo

Task types are set in the Task Information > Advanced tab. http://www.intaver.com/images/RP_Forum_Advanced.png To understand how Task types work it is useful to think of a 3-sided triangle in which the sum of the lengths of the sides always have to add up to fixed value eg. 100. With the added condi...
by Intaver Support
Mon Feb 05, 2018 11:00 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Maximum task duration
Replies: 1
Views: 1156

Re: Maximum task duration

RiskyProject has a define maximum task duration of 7300 days. Keep in mind that it is considered best practice to limit tasks to a maximum of 44 days by the DCMA 14 points inspection. Obviously, there are exceptions, but it is best to break down tasks to the smallest possible discrete activities.
by Intaver Support
Mon Feb 05, 2018 10:32 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Launching 3rd Party tools from RiskyProject
Replies: 1
Views: 1174

Re: Launching 3rd Party tools from RiskyProject

With the release of RiskyProject 7, you can no longer add additional 3rd party tools to the Launch menu. RiskyProject now only supports the launching of Microsoft Project directly from RiskyProject.
by Intaver Support
Fri Jan 19, 2018 8:58 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Maximum task durations affect on the simulation results
Replies: 1
Views: 1179

Re: Maximum task durations affect on the simulation results

It depends on the action that you select if a deadline is met. No Actions: displays a deadline indicator but will not affect the results of the simulation End task: ends the task any time the deadline duration is exceeded, so the simulation results will not show any duration greater than the deadlin...
by Intaver Support
Fri Jan 19, 2018 8:56 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying Risk Matrix colors
Replies: 3
Views: 1681

Re: Modifying Risk Matrix colors

As long as you know the colors that you want to use for your risk matrix, you can modify the risk matrix colors very quickly On the Ribbon, go to Risks > Format Risk Matrix. The Format Risk Matrix dialog opens. We recommend that you set up your color palette first. You can defined your custom palett...
by Intaver Support
Fri Jan 19, 2018 8:53 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Comparing Cost of Risk
Replies: 1
Views: 1299

Re: Comparing Cost of Risk

There is no set answer for this, it really depends upon what your objective is for calculating the cost of risk and how it will be used for managing your projects. In a typical scenario, the two baselines would represent pre and post mitigated baselines where the post mitigated includes the cost and...
by Intaver Support
Fri Jan 12, 2018 6:23 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Maximum number of tasks
Replies: 1
Views: 1065

Re: Maximum number of tasks

If you use RiskyProject standalone without importing schedule from other project management software, such as Microsoft Project or Primavera, maximum number of tasks is 20,000. If you are importing schedule from other software, total number of tasks equals number of task in original schedule plus 20...
by Intaver Support
Fri Jan 12, 2018 6:18 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Stat::Fit
Replies: 1
Views: 1131

Re: Stat::Fit

If you have empirical data for Cost, Income, and Duration, you may use Stat::Fit software to generate most appropriate statistical distribution. You cannot use Stat::Fit for start time. Stat::Fit is the third party software by Geer Mountain Software (http://www.geerms.com) and can be purchased separ...
by Intaver Support
Fri Jan 12, 2018 6:16 pm
Forum: Project Portfolio Risk Management
Topic: Connection to remote database
Replies: 1
Views: 1234

Re: Connection to remote database

1. On the server Start Microsoft SQL Server Management Studio 2. Right click on the server and select the Properties option. 3. In the Server Properties dialog under the Connections tab check the Allow remote connections to this server option: http://www.intaver.com/images/RP_Forum_RemveDB1.png 4. G...