Search found 1031 matches

by Intaver Support
Thu May 14, 2009 3:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 172400

Here is link to RiskyProject online help system. It includes detailed description of all new features of RiskyProject 3:

for RiskyProject Professional:
http://www.intaver.com/Help3/RP3_Help_Content.html

for RiskyProject Lite:
http://www.intaver.com/Help3/RP3_HelpLite_Content.html
by Intaver Support
Thu May 14, 2009 3:07 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Importing MS Project data
Replies: 7
Views: 54839

RiskyProject 2.1 did not support different resource calendar. However RiskyProject 3.1 was data model very similar to Microsoft Project. It has task calendar, resource calendar, and project calendar. You can download new version RiskyProject 3.1 from http://www.intaver.com/index-downloads.html You m...
by Intaver Support
Thu Apr 16, 2009 10:15 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 172400

RiskyProject 3.1 is released

RiskyProject 3 is released April 14, 2009. Here is a description of some new features: Non-schedule risks and user-defined risks outcomes RiskyProject 3 performs quantitative risk analysis on any types of risks outcomes including non-schedule risks. Non-schedule risk are risks that are not related t...
by Intaver Support
Wed Apr 01, 2009 12:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Duration convergence affecting Cost Validity?
Replies: 1
Views: 21294

We recommend creating one task and assign multiple risks, related to cost to this task. If you are using fixed cost increase risks, you need to define some fixed cost for this task. In RiskyProject 2.1 by default number of simulation will be 100. It may be insufficient, therefore to may go to Tools ...
by Intaver Support
Mon Mar 09, 2009 8:07 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Implementation of event chain methodology
Replies: 4
Views: 46250

RiskyProject 3 has new features directly related to Event Chain Methodology: 1. Event chain diagrams, which present threats and opportunities with their probabilities and impact. 2. None-schedule risks: safety, environment, technology, quality, etc. 3. Ability to rank all risks (schedule and non-sch...
by Intaver Support
Mon Mar 09, 2009 7:59 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Import risks from MS Acess
Replies: 1
Views: 19960

RiskyProject does not include standard tools to read data from Access database. RiskyProject currently can read data only from WelcomRisk database (Microsoft SQL Server or Oracle DB). However our rapid response team implements adapters which can read risk data from any databases. Most adapters are v...
by Intaver Support
Fri Feb 13, 2009 8:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 172400

RiskyProject 3 is designed for such types of analysis. We apply methodology derived from Analytical Hierarchy Process (AHP). We perform pair-wise comparison. This way we determine weight for each risk. For example, if there is a safety risk and cost risk you may enter that safety is 4 times more imp...
by Intaver Support
Thu Jan 08, 2009 7:43 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 67366

You may now see event chain diagrams in RiskyProject version 3 beta.
by Intaver Support
Thu Jan 08, 2009 7:42 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Import new schedule from MS Project and keep risks
Replies: 2
Views: 27531

You may do it using File -> Import ->Import XML instead of File -> Open. 1. Open your old file in RiskyProject with assigned risks 2. Click on File -> Import 3. Select that you want to keep risks 4. Click OK RiskyProject would keep risks assigned to tasks based on unique task ID from MS Project. Whe...
by Intaver Support
Fri Dec 19, 2008 5:00 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 172400

Intaver Institute Inc. released RiskyProject version 3. RiskyProject 3 includes the following features: - Risk register: manage threats, opportunities, and issues using fully searchable risk register - Analysis of multiple risk mitigation plans: select what plan would be most effective in your proje...
by Intaver Support
Thu Nov 27, 2008 4:04 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 67366

We recently posted a presentation regarding RiskyProject 3. You can find a slide with event chain diagram at: http://www.intaver.com/riskyproject_presentations.html. You would see arrows associated with risks (down) and opportunities (up).
by Intaver Support
Thu Nov 27, 2008 4:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Academic License
Replies: 5
Views: 42862

We issue free academic license only for educational institutions, such as colleges and universities. In your case you need to purchase a full license.
by Intaver Support
Tue Nov 18, 2008 1:17 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 172400

RiskyProject alpha version was release November 10, 2008. Please visit: http://www.intaver.com/riskyproject_presentations.html for the preview of RiskyProject 3 new features. RiskyProject 3 Beta will be released November 28, 2008.
by Intaver Support
Tue Nov 18, 2008 4:05 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Low, base and high resource allocation
Replies: 3
Views: 32345

Low, base and high resource allocation is calculated based on low, base, and high results of project schedule analysis. For example, the resource is assigned to the task with the uncertain duration. Low resource allocation would correspond with low task duration (P10).
by Intaver Support
Tue Nov 18, 2008 4:01 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Distribution for the moment of risk
Replies: 1
Views: 25487

You can specify statistical distribution for the moment of risk. It has nothing to do with probability of risk occurrence. Statistical distribution for the moment of risk specifies time when the risk would occur during the course of task (in percents). For example, uniform distribution means with st...