Search found 995 matches

by Intaver Support
Sun Jan 17, 2021 9:05 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Assigning Uncertainty to Entire Project
Replies: 1
Views: 13978

Re: Assigning Uncertainty to Entire Project

Here is the easiest way to assign uncertainties to entire project: 1. Select every task – Click on first task ID and drag down. 2. Right-click on a Task ID to open the shortcut menu. 3. Click on Set Low/High Duration. 4. Enter in the coefficients and select the Statistical Distribution and click OK....
by Intaver Support
Sun Jan 17, 2021 8:57 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Schedule Consolidation to optimize large schedules for analysis
Replies: 1
Views: 13244

Re: Schedule Consolidation to optimize large schedules for analysis

Schedule Consolidation is a feature included with the release of version 7.1 and is used to create a “consolidated schedule” that is an equivalent project schedule with equal cost and duration and cost but with less activities and therefore can decrease time required to run an analysis. Consolidatio...
by Intaver Support
Sun Dec 13, 2020 1:46 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject icons in the status bar
Replies: 1
Views: 14372

Re: RiskyProject icons in the status bar

When you try to open file, save file, export, import information, open or save RiskyProject templates, or perform any other operations with files in RiskyProject, RiskyProject launches a separate application called RiskyProjectOpen.exe. This application gets file path and reports it to RiskyProject....
by Intaver Support
Sun Dec 13, 2020 1:37 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying the Incident Statistics view color scheme
Replies: 1
Views: 15420

Re: Modifying the Incident Statistics view color scheme

By default, the Incidents have the same number of classifications as the Risk Matrix. Yes, if you open the incidents tab, click Classifications. The Incident Classifications Settings dialog box opens. http://www.intaver.com/images/RP_Forum_IncidentColor.png Select the classification that you want to...
by Intaver Support
Sun Dec 13, 2020 1:31 pm
Forum: Project Portfolio Risk Management
Topic: Enable/Disable Incident Reporting
Replies: 1
Views: 15008

Re: Enable/Disable Incident Reporting

The Incidents modules can be disabled in the Portfolio Options. Normally, Incidents are disabled by default, so it maybe that someone accidentally enables them during the install or configuration process. To disable the Incidents module, on the Projects tab, Portfolio Settings group, click Portfolio...
by Intaver Support
Mon Nov 16, 2020 7:05 pm
Forum: Project Portfolio Risk Management
Topic: RiskyProject Professional vs RiskyProject Enterprise
Replies: 2
Views: 44399

Re: RiskyProject Professional vs RiskyProject Enterprise

RiskyProject Professional is best suited or the analysis and management of projects by a single user. RiskyProject Professional is desktop software that provides project risk analysis and management. This includes cost and schedule risk analysis using Monte Carlo simulations. RiskyProject Profession...
by Intaver Support
Mon Nov 16, 2020 7:04 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: How RiskyProject Enterprise licensing works?
Replies: 1
Views: 14602

Re: How RiskyProject Enterprise licensing works?

RiskyProject Enterprise is a client/server application which requires client and server licensing which are separate as the desktop licenses can work either in standalone mode or as a client connected to the Enterprise Server. The Enterprise Server license does not just allow users to connect to a d...
by Intaver Support
Mon Nov 16, 2020 6:23 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying Risk Outcome Distributions
Replies: 1
Views: 15586

Re: Modifying Risk Outcome Distributions

On every risk assignment that has a 3 point estimate (low, base, high) you adjust the statistical distribution parameters. 1. Locate the risk assignment in any of the views where they can be edited such as the Task Information > Risks tab, Risk Information > Probabilities and Impacts tab, or the Ris...
by Intaver Support
Thu Oct 15, 2020 11:13 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Moving a 7.1 version file to an earlier version
Replies: 1
Views: 15047

Re: Moving a 7.1 version file to an earlier version

RiskyProject versions are always backwards compatible, but not forward. So you can open a 7.0 file in 7.1, but not the reverse. This is because the data schemes are different between major versions. Because the underlying data schema is different, we can only offer a partial solution of moving the s...
by Intaver Support
Thu Oct 15, 2020 11:09 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: XML export results are not the same in RiskyProject and MSProject
Replies: 1
Views: 14099

Re: XML export results are not the same in RiskyProject and MSProject

We have looked at this in a little more detail and the reason is not because of differences in the algorithm, it is because the nature of probabilistic data. In this case, the P85 finish time of the predecessor and start time of the successor are correlated but do not represent a calculated schedule...
by Intaver Support
Thu Oct 15, 2020 10:58 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject Licesing
Replies: 1
Views: 14942

Re: RiskyProject Licesing

Due to the way the MS installation process and the UAC interact. RiskyProject license are assigned per user account in thee registry under HKEY_CURRENT_USER. RiskyProject can be installed on one computer and accessible from all accounts, as long as each account has a license. If many users logon to ...
by Intaver Support
Sun Oct 04, 2020 9:50 pm
Forum: Project Portfolio Risk Management
Topic: Integration with Asta PowerProject
Replies: 2
Views: 20488

Re: Integration with Asta PowerProject

We have many clients who asked as did we actually tried to performed risk analysis based on schedules created in Asta Powerproject. Yes. We tried many schedules created in Asta and import them to RiskyProject. Asta and RiskyProject are compatible with each other. You can use both XML export from Ast...
by Intaver Support
Sun Oct 04, 2020 9:39 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Generating seed numbers using formula fields
Replies: 1
Views: 13826

Re: Generating seed numbers using formula fields

Seed values are fundamental to generating the random numbers that are required for the Monte Carlo simulation. They are generated randomly by our system, but once set, the values that are sampled from the statistical distributions during each iteration are deterministic. So, If two task have the sam...
by Intaver Support
Sat Sep 19, 2020 12:25 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Probabilistic vs Weather Calendar
Replies: 4
Views: 28289

Re: Probabilistic vs Weather Calendar

Weather calendar is more intuitive and should be based on reliable historical data about weather events. Bag weather days are almost universally available from public sources.
by Intaver Support
Sat Sep 19, 2020 12:23 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Task Icons
Replies: 3
Views: 24136

Re: Task Icons

You cannot disable task icons. They are useful to identify type of task. These icons are also present in risk register, incident register and other views. W