Search found 998 matches

by Intaver Support
Thu Jul 27, 2023 1:08 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Setting a statistical distribution for group of tasks
Replies: 2
Views: 15377

Re: Setting a statistical distribution for group of tasks

We recommend to use Uncertainty Bands for settings distributions for cost and duration for the group of tasks. Such approach makes setting uncertainties most consistent across the project. In case of RiskyProject Enterprise uncertainty band information is saved in RiskyProject database, which makes ...
by Intaver Support
Thu Jul 27, 2023 1:04 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Criticality Index
Replies: 2
Views: 15145

Re: Criticality Index

After the column with the criticality index is inserted to the grid, the grid information will be saved in to ALM file. So when you reopen project file this column will be presented. It is also possible to save column layout for all future new projects. It is done using Schedule -> Project Options -...
by Intaver Support
Thu Jul 27, 2023 12:58 pm
Forum: Project Portfolio Risk Management
Topic: Schedule Reports that show Uncertainty Bands.
Replies: 2
Views: 14028

Re: Schedule Reports that show Uncertainty Bands.

It is important to note that all information about Uncertainty Bands in RiskyProject Enterprise are saved into the Enterprise database. As a result the users in one organization will be able to share settings for the uncertainty bands. Only administrator are able the edit and save these settings. Th...
by Intaver Support
Mon Jul 03, 2023 10:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Viewing or Converting Labour Days to Calendar Days
Replies: 1
Views: 3863

Re: Viewing or Converting Labour Days to Calendar Days

Calendar days are referred to as “elapsed days” or edays. Use of elapsed duration setting in the Advanced Settings in the desktop version when you import schedule from Microsoft Project. It is because the letter that is used to denote elapsed days is dependent upon the language settings. http://www....
by Intaver Support
Mon Jul 03, 2023 10:03 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License Activation Already Activated Message
Replies: 1
Views: 2838

Re: License Activation Already Activated Message

We can refresh the license, but this will continue to happen as it appears that the license information cannot be written to your computers registry. Typically this occurs when there are insufficient user permissions to write to the license information to the registry, a utility is removing "unautho...
by Intaver Support
Mon Jul 03, 2023 5:49 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Pre and Post-Mitigation Simulation Results
Replies: 1
Views: 3096

Re: Pre and Post-Mitigation Simulation Results

The problem appears to be that you have not created a post mitigated baseline with reduced probabilities etc due to the mitigation activities. Assigning mitigation activities in the waterfall chart are only a forecast but do not impact the simulation results. To create a post mitigated baseline, you...
by Intaver Support
Sun Apr 02, 2023 11:15 am
Forum: Project Portfolio Risk Management
Topic: RiskyProject Professional vs RiskyProject Enterprise
Replies: 2
Views: 45188

Re: RiskyProject Professional vs RiskyProject Enterprise

In addition to other features shown above RiskyProject Enterprise integrates with Proteus Envision. Please visit https://sna-software.com/proteus-envision/ for information about this product.
by Intaver Support
Sun Apr 02, 2023 11:13 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Outcomes vs Moment of Risk
Replies: 2
Views: 57858

Re: Risk Outcomes vs Moment of Risk

We did some analysis, how moment of risk affects results of Monte Carlo schedule risk analysis. We would that in some cases different settings of Moment of Risk may affect results, such as mean project duration and cost, very significantly. We recommend to carefully analyze the Moment of Risk if you...
by Intaver Support
Sun Apr 02, 2023 11:08 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Scaling risk form
Replies: 2
Views: 36296

Re: Scaling risk form

This scaling is likely related to a monitor display setting. We have found with some HD displays Windows doesn't scale the application properly. In this cases it is displaying all the fields, but not scaling correctly. This is a known issue and particularly if your setup includes multiple monitors w...
by Intaver Support
Sat Jan 07, 2023 3:27 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Import mitigation plans
Replies: 1
Views: 4602

Re: Import mitigation plans

Using the Import > Risks from Excel feature, you can now import mitigation plans with updates. https://www.intaver.com/images/RP_Forum_MitExcel.png Each row of such Excel file is a mitigation plan assigned to particular risk; such file must have mitigation name and associated risk as a separate colu...
by Intaver Support
Sat Jan 07, 2023 3:22 pm
Forum: Project Portfolio Risk Management
Topic: Mitigation Waterfall Chart
Replies: 1
Views: 4418

Re: Mitigation Waterfall Chart

With the release of version 7.2, we have added significant new mitigation planning capabilities of which required the addition of an additional mitigation view as the existing views were designed to support the new capabilities. One of the main changes is the ability to track planned and actuals imp...
by Intaver Support
Sat Jan 07, 2023 3:13 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: JCL chart
Replies: 1
Views: 32094

Re: JCL chart

Joint confidence level chart can be accessed from Project Summary view in the Analysis tab of Workflow menu or ribbon: https://www.intaver.com/images/RP_Forum_JCL1.png In the latest release of the software Joint confidence level chart includes frontier lines or lines with equal probabilities of cost...
by Intaver Support
Wed Nov 23, 2022 8:04 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Scaling risk form
Replies: 2
Views: 36296

Re: Scaling risk form

You probably see Risk Form like this: https://www.intaver.com/images/RP_Forum_RiskFormProblem.png In Windows 10 you may try to run to follows these steps: 1. Open Settings, and click/tap on the System icon. 2. Click/tap on Display on the left side, and click/tap on the Advanced scaling settings link...
by Intaver Support
Wed Nov 23, 2022 7:41 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Expected Loss
Replies: 1
Views: 4290

Re: Expected Loss

Expected cost of risk is calculated based on formula: ------------------------------------------- (Mean cost of project - Original (deterministic) cost of project) * cost correlation coefficient of this risk ------------------------------------------- It means that expected cost is this is a contrib...
by Intaver Support
Wed Nov 23, 2022 7:31 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Updating Risk Assignments
Replies: 1
Views: 6042

Re: Updating Risk Assignments

There are two methods that we recommend. First is the Risk Assignment view. Here this lists all risk assignments to task or resources. Here probability, impacts, and statistical distributions can be updated for each task individually. https://www.intaver.com/images/RP_Forum_RiskView.png 2nd method i...