Search found 992 matches

by Intaver Support
Tue Apr 18, 2006 10:15 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New Reports for Risky Project
Replies: 4
Views: 29188

You have raised a very interesting question about filtering. We are planning to implement the filtering in the next versions. The issue is almost all parameters in RiskyProject are not single values. They are distributions or arrays of different outcomes. The example is the cost associated with reso...
by Intaver Support
Mon Apr 17, 2006 2:14 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New Reports for Risky Project
Replies: 4
Views: 29188

Hello Steve, You can customize your reporting in current RiskyProject version: 1. You can insert or hide columns in any views, including resource view. To do it just right click on the column's header with each datasheet. 2. Then you can select rows in the datasheet and copy them to clipboard. To do...
by Intaver Support
Sun Apr 09, 2006 9:06 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Calculating Results
Replies: 6
Views: 35876

convergence

If you set high convergence (low % and high number of iterations) this will give you the most accurate risk analysis on your project. However, on large projects, this could take a longer amount of time to complete. So there is a tradeoff.

Hope this has helped.

Intaver Support
by Intaver Support
Sun Apr 09, 2006 9:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Calculating Results
Replies: 6
Views: 35876

Optimall convergence settingsg

Hi, There are no "optimal" settings that would apply to all projects. When setting the convergence, the lower the change (%) and higher number of iterations the longer it will take a projects results to converge and the longer your calculations will run. We recommend that if you are looking for as a...
by Intaver Support
Sun Apr 09, 2006 10:00 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Calculating Results
Replies: 6
Views: 35876

Use convergence setting in Options.

Hi In the Options dialog box, Calculation tab use the Monte Carlo convergence settings. Here is our glossary definition of convergence In the process of Monte Carlo simulation RiskyProject monitors mean and standard deviation of project duration. RiskyProject then calculates relative different betwe...
by Intaver Support
Sat Apr 01, 2006 10:01 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Moment of risk

Moment of risk is defined by The moment of risk is uses in tracking to automatically calculate the chance of a risk for partially completed tasks, in task cancellation, in risk "restart task". So iif you put a trianglar distribution for a risk that start at A% of the task duration, and has a most li...
by Intaver Support
Sat Apr 01, 2006 9:54 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Defining risk types in a project

No, the risk types must be all the same.
by Intaver Support
Sat Apr 01, 2006 9:50 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Defing risk chance type

Go to Options -> Risk and define the risk chance calculation. The chance can be absolute or relative.
by Intaver Support
Tue Mar 28, 2006 10:02 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Summary charts

This is planned for our Fall 2007 release of RiskyProject. We are building a couple of distinct views actuals/accruals for this release.
by Intaver Support
Tue Mar 28, 2006 9:52 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: What industry RiskyProject is mostly present in?
Replies: 13
Views: 176018

Aerospace users

We have a number of clients in the aerospace industry. We recently presented our product RiskyProject and our Event Chain Methodology to the Space System Engineering and Risk Management Symposium in Los Angeles. RiskyProject is used in aero-space business for analysis of project schedules in differe...
by Intaver Support
Tue Mar 28, 2006 9:49 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Max number of risks

RiskyPRoject can handle up to 3000, however we don't recommend to enter that many as it is hard to analyze them.
by Intaver Support
Tue Mar 28, 2006 9:46 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Analysis Results
Replies: 17
Views: 89105

Exactly

The values between p10 and p90 represent 80% of the uncertainty for the variable that you are looking at.


Intaver Support
by Intaver Support
Tue Mar 28, 2006 8:27 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Short summary of Event Chain Methodology
Replies: 6
Views: 37233

Patent info

Our event chain methodology has been filed with the US PTO

Intaver Support
by Intaver Support
Sun Mar 26, 2006 10:23 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject integration with SciForma
Replies: 3
Views: 26446

Unfortunately, no.

Intaver Institute is an integration partner with Sciforma. We don’t resell and don’t provide any support for the PS8 software