Search found 992 matches

by Intaver Support
Sun Mar 09, 2008 11:32 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License Is Taken Message
Replies: 7
Views: 36467

Yes. We allow our clients to use one RiskyProject license on home and business computer. Please contact Intaver Institute (sales@intaver.com or info@intaver.com) or call us (403)6922252
by Intaver Support
Sun Mar 09, 2008 11:23 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to create own risk template
Replies: 6
Views: 30486

If you have your own risks template and want to share it with our client please send as a note at sales@intaver.com or info@intaver.com. You may also post it within this forum With your permission we may include your risks template to the standard set of risk templates, which come with RiskyProject.
by Intaver Support
Sun Mar 09, 2008 11:19 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Work calculation in RiskyProject
Replies: 3
Views: 23286

Ms Project uses three resource views:
- resource sheet
- resource chart
- resource usage.
I think you are taking about resource usage sheet, which we are planning to create in the next version RiskyProject 3. We agree that it is very convenient way to define actual work.
by Intaver Support
Sun Mar 09, 2008 11:17 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Mitigation Tab
Replies: 9
Views: 41812

Since we move towards advance managing of mitigation plans includin mitigation history, I would a good idea to rename Mitigation View. We think that this name may cause some confusion.
by Intaver Support
Tue Feb 19, 2008 4:33 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Low and high duration for group of tasks
Replies: 2
Views: 18853

This feature is currently implemented in RiskyProject 3. If you wish to try it please feel free to request beta version of the RiskyProject 3. Just send us e-mail to sales@intaver.com or info@intaver.com. Please note that we implemented not only automatic calculation of low and high duration, but al...
by Intaver Support
Tue Feb 05, 2008 12:26 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to create own risk template
Replies: 6
Views: 30486

Here is what should you do: 1. Define you risk breakdown structure in global risk view 2. Go to Tools->Save Risk Template 3. When you go to Tools->Open Risk Template, you will be able to see the risk template within the list Please remember that risk templates are saved as a file with extension *.al...
by Intaver Support
Tue Feb 05, 2008 12:16 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risk Mitigation Tab
Replies: 9
Views: 41812

Yes. Risk Mitigation view is designed for such problems. Another example of this is the delay with the delivery of component. If you wait for one component, you don't necessary need to wait for another component. Here is what you can do in RiskyProject. 1. Define two risks: "Delay with delivery of t...
by Intaver Support
Tue Jan 29, 2008 5:22 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: How can I export results of analysis back to MS Project?
Replies: 1
Views: 15471

You can export result back to MS Project by going to Tools->Schuling Software->Microsoft Project. RiskyProject will ask you what do you want to export: baseline or results. In your case you need to select results. Results will be exported as temporary MPX file. MS Project will be launched automatica...
by Intaver Support
Tue Jan 22, 2008 1:41 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: How to see Event Chain Diagram?
Replies: 9
Views: 41565

Event chain diagrams will be implemented in RiskyProject 3, which supposes to be released Q3, 2008. Event chain diagram will present risks with their probability and impact on the Gantt chart as arrows. All Gantt Chart (input data, results, tracking, success rate, etc.) will have the options to disp...
by Intaver Support
Mon Jan 21, 2008 12:40 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New features
Replies: 18
Views: 74541

Here is list of RiskyProject 3 features: 1. Project management with risk and uncertainties using Critical Chain (CCPM) - calculation of the buffer based on risk and uncertainties in display view: buffer vs time - view chance of completion vs. time 2. Multiple baselines, will be used to CCPM. Multipl...
by Intaver Support
Tue Jan 15, 2008 5:55 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Risk correlations
Replies: 13
Views: 51929

Risk Correlations can be entered in Risk Information Dialog for local and global risks. You may access this dialog by double clicking on RiskID within a list of local risks or in global risk view. You need to select the risk, current risk will be corrected with.
by Intaver Support
Tue Jan 15, 2008 5:53 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Enterprise version of RiskyProject
Replies: 3
Views: 25579

RiskyProject v. 3 will be released Q1, 2008. RiskyPortfolio will be released Q2-Q3, 2008
by Intaver Support
Tue Jan 15, 2008 5:51 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Enterprise version of RiskyProject
Replies: 3
Views: 25579

Intaver Institute is activelly working on a new product called RiskyPortfolio. RiskyPorfolio is web-based software fully integrated with RiskyProject via database. Here are main features of RiskyPortfolio: - Risk Management: risk identification, analysis, response planning - Estimation and forecasti...
by Intaver Support
Wed Jan 02, 2008 4:24 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject for cost analysis
Replies: 7
Views: 31715

You may use negative result for fixed cost increase and relative cost increase events. For example you have event 'saving related to the component' with fixed cost increase outcome -$1000. I would mean that this event would lead to $1000 savings for this component.
by Intaver Support
Wed Jan 02, 2008 4:18 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject for cost analysis
Replies: 7
Views: 31715

RiskyProject can be used for project cost analysis. You should have a project schedule and list of risks, which would affect your cost. RiskyProject will calculate probabilistic cash flow profile for your project. You may use event with the following outcomes: fixed cost increase relative cost incre...