Search found 992 matches

by Intaver Support
Sun Jun 06, 2021 12:45 pm
Forum: Project Portfolio Risk Management
Topic: Schedule Reports that show Uncertainty Bands.
Replies: 2
Views: 12781

Re: Schedule Reports that show Uncertainty Bands.

Short answer is no. I was thinking that they could be flagged in a text column and filtered but our Text columns do not support filtering. Workaround might be to use a Text Column to flag activities that use Risk Bands > Export the Schedule the Excel and apply the filter to the target column (Risk B...
by Intaver Support
Sun Jun 06, 2021 12:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Importing Costs from Excel
Replies: 1
Views: 12849

Re: Importing Costs from Excel

Currently, we don't this capability implemented directly. We do integrate with Excel, but where you can import data is limited to: - import risk register with their properties - import probabilities and impact of risks. Excel import is expandable in that we can link to additional fields, we would re...
by Intaver Support
Tue May 04, 2021 9:24 pm
Forum: Project Portfolio Risk Management
Topic: Analyzing mega schedules
Replies: 2
Views: 24931

Re: Analyzing mega schedules

In depends on schedule, particularly on number of repeated activities. We tried this algorithm on very many real life schedules. If schedule is relatively small, for example, less than 1000-1500 activities, in our experience reduction will be 5-10%. Some large schedule contain many repeated activiti...
by Intaver Support
Tue May 04, 2021 9:16 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculating the Cost of Residual Risk
Replies: 3
Views: 16222

Re: Calculating the Cost of Residual Risk

If you have assigned a cost to a mitigation plan and assigned it to a risk this is used only for the post-mitigation calculation and does not affect the simulation results. For example, we create a response plan in the Mitigation/Response view with a Cost of $25000. http://www.intaver.com/images/RP_...
by Intaver Support
Tue May 04, 2021 9:10 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Configuring Risk Matrix for Quantitative Risk Analysis
Replies: 1
Views: 12508

Re: Configuring Risk Matrix for Quantitative Risk Analysis

The reason for this for qualitative risk analysis standard 5 x 5 risk matrix works well as you are only "placing" the risk onto the matrix using a simple probability x impact with subjective scores (1,2,3,4,5) or labels (very low, low,.. etc), From this you get a simple score e.g 3*5= 15 and the ris...
by Intaver Support
Tue Mar 23, 2021 1:00 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Setting Chart defaults
Replies: 2
Views: 17807

Re: Setting Chart defaults

Chart defaults for all projects at the same time can be defined in RiskyProject Enterprise. In this case you can setup any portfolio settings, save it in database and these settings will be consistent for all projects.
by Intaver Support
Tue Mar 23, 2021 12:55 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculating the Cost of Residual Risk
Replies: 3
Views: 16222

Re: Calculating the Cost of Residual Risk

In most cases, the “Cost of Residual Risk” is the same as the Potential loss. This may sound odd, but mitigation plans normally only lower the probability of risks as this is the most cost efficient. Experience shows that lowering the impacts of a risk often are normally not cost effective. However,...
by Intaver Support
Tue Mar 23, 2021 12:51 pm
Forum: Project Portfolio Risk Management
Topic: Cost Before Mitigation Property
Replies: 1
Views: 12885

Re: Cost Before Mitigation Property

The most probable cause of this issue is that the “Auto Calculation of Expected Loss” is enabled in the Risk Information > Properties tab. The feature introduced in version 7.1 automatically calculates the expected loss if the risk occurs. The calculation does not include probability. It is useful e...
by Intaver Support
Thu Feb 25, 2021 1:51 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Applying level of uncertainty using PERT to entire project
Replies: 1
Views: 13177

Re: Applying level of uncertainty using PERT to entire project

PERT analysis is different than Monte Carlo simulation. However, using Triangular statistical distribution is analogous distribution when running simulations. While there are several different ways to apply statistical distributions (uncertainty) to activities here is the quickest way: 1. Select eve...
by Intaver Support
Thu Feb 25, 2021 1:43 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Criticality Index
Replies: 2
Views: 14015

Re: Criticality Index

Yes, with the most recent version 7.1, criticality index was added to on the KPIs that can be calculated during Monte Carlo simulations. As calculating the criticality index requires a critical path calculation, critical path calculation must be enabled in the Options > Calculations > Calculate Crit...
by Intaver Support
Thu Feb 25, 2021 1:39 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Exporting results of analysis to P6
Replies: 1
Views: 15049

Re: Exporting results of analysis to P6

The results of the analysis can be exported back to P6 using the XML export. The xml format is in a Microsoft Project format that is supported by P6. Documentation on how to import the MSP xml into p6 can be found here: https://docs.oracle.com/cd/E17266_01/p6help/help/en/helpmain.htm?toc.htm?8010.ht...
by Intaver Support
Sun Jan 17, 2021 9:19 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: I'm running 1000 simulations for project in my project schedule
Replies: 1
Views: 13196

Re: I'm running 1000 simulations for project in my project schedule

It depends on schedule. In most real life projects 600 - 800 iterations will give very accurate results. Remember that accuracy of analysis should correspond with accuracy of input data. Input probability and outcome of risks as well as uncertainties, defined by statistical distribution of task dura...
by Intaver Support
Sun Jan 17, 2021 9:05 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Assigning Uncertainty to Entire Project
Replies: 1
Views: 13566

Re: Assigning Uncertainty to Entire Project

Here is the easiest way to assign uncertainties to entire project: 1. Select every task – Click on first task ID and drag down. 2. Right-click on a Task ID to open the shortcut menu. 3. Click on Set Low/High Duration. 4. Enter in the coefficients and select the Statistical Distribution and click OK....
by Intaver Support
Sun Jan 17, 2021 8:57 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Schedule Consolidation to optimize large schedules for analysis
Replies: 1
Views: 12857

Re: Schedule Consolidation to optimize large schedules for analysis

Schedule Consolidation is a feature included with the release of version 7.1 and is used to create a “consolidated schedule” that is an equivalent project schedule with equal cost and duration and cost but with less activities and therefore can decrease time required to run an analysis. Consolidatio...
by Intaver Support
Sun Dec 13, 2020 1:46 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject icons in the status bar
Replies: 1
Views: 13991

Re: RiskyProject icons in the status bar

When you try to open file, save file, export, import information, open or save RiskyProject templates, or perform any other operations with files in RiskyProject, RiskyProject launches a separate application called RiskyProjectOpen.exe. This application gets file path and reports it to RiskyProject....