Search found 992 matches

by Intaver Support
Sun Jun 24, 2007 7:31 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject 2.1 new features
Replies: 1
Views: 16589

Here is few features of RiskyProject 2.1 1. RiskyProject can now open Microsoft Project MPP file (RiskyProject Professional only). Just go to File -> Open and select MPP file format. 2. Local risk views: Local risks views help to assign risks to one or many tasks or resources. 3. Improved calendars:...
by Intaver Support
Sun Jun 24, 2007 7:30 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: RiskyProject 2.1
Replies: 4
Views: 23413

RiskyProject 2.1 can be installed together with previous versions of RiskyProject (uninstall does not required). All current users of RiskyProject can upgrade the software free of charge. RiskyProject Lite and Professional 2.1 will use license of previous RiskyProject versions. You may download Risk...
by Intaver Support
Thu Jun 07, 2007 4:43 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Printing frequency diagrams
Replies: 1
Views: 16852

You can print frequency and cumulative probability diagrams for complete project when you click on Print in Project summary.

You may also save chart to clipboard. To do it right click on the chart and select format you want to use. Then you may paste this chart to your PowerPoint presentation.
by Intaver Support
Thu Jun 07, 2007 4:39 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: ECM and CPM
Replies: 4
Views: 25360

Event chain methodology is based on CPM and Monte Carlo simulation. It also includes a number of other principles which simplify modeling uncertainties in project schedules and make it much more accurate. Among such principles: a. Analysis of the moment of the risk b. Managing chain of events c. Eve...
by Intaver Support
Tue May 08, 2007 2:50 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Critical chain
Replies: 1
Views: 17300

We consider Event chain methodology as a next step beyond Critical chain. Event chain methodology is uncertainty modeling and schedule network analysis technique, which focuses on managing events and event chains in the project schedule. Here is how our clients are using Event chain methodology: 1. ...
by Intaver Support
Tue May 08, 2007 2:36 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New RiskyProject version
Replies: 1
Views: 18992

Here is the list of new features of RiskyProject 2.1: 1. Ability to open Microsoft Project MPP file (only for RiskyProject professional) 2. Improved probabilistic and conditional branching 3. Improved calculation performance 4. Full compatibility with Microsoft Vista 5. Improved calendars 6. Local r...
by Intaver Support
Tue May 01, 2007 6:32 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Primavera P5/RiskyProject integration
Replies: 4
Views: 26949

In order to use RiskyProject with Primavera to need to export Primavera data to MPX or Microsoft Project XML formats. Please note, that in order to export data to Microsoft Project XML you must have MS Project installed on the same computer as Primavera. Then you can import MPX or XML file to RiskyP...
by Intaver Support
Tue May 01, 2007 6:20 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Event cost
Replies: 1
Views: 19436

Event cost is not currently calculated by RiskyProject however, we are planning to implement it next releases. We agree that event cost would be very good indicator of criticality of each event. It will be calculated based on correlation coefficient associated with cost of task and cost of project.
by Intaver Support
Fri Apr 13, 2007 10:39 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Monte Carlo for Event Chain Methodology
Replies: 1
Views: 20602

Monte Carlo simulation is used in Event chain methodology to perform analysis of project schedules. Once events and event chains are defined, quantitative analysis using Monte Carlo simulation can be performed to quantify the cumulative impact of the events. Probabilities and impacts of risks are us...
by Intaver Support
Mon Apr 09, 2007 11:54 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: New version of RiskyProject
Replies: 1
Views: 19765

Next version of RiskyProject 2.2 supposes to be released in next couple of weeks. New features will include: 1. Support native Microsoft Project MPP file format 2. Improved integration with Microsoft Project 2007 3. Improved visualization of probabilistic and conditional branching 4. Local risk view...
by Intaver Support
Mon Apr 09, 2007 11:43 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: RiskyProject and VISTA
Replies: 3
Views: 23710

We are happy to let you know, that RiskyProject 2.0 is fully compatible with Microsoft Windows Vista. We have extensively tested our software with different versions of Microsoft Windows Vista and did not find any problems and conflicts.
by Intaver Support
Mon Apr 09, 2007 11:37 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: MPX Export to MS Project 2007
Replies: 2
Views: 20539

Yes, MSP2007 and early versions of MS Project process MPX file slightly different. We are currently in the process of releasing new version for RiskyProject 2.1. It should fully support Microsoft Project 2007. This version should be available within next couple of weeks.
by Intaver Support
Wed Mar 28, 2007 11:28 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Event chain diagrams
Replies: 1
Views: 17669

We don't implement Event chain diagrams, but planning to to it in next releases of RiskyProject
by Intaver Support
Wed Mar 28, 2007 11:27 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Risks for resources
Replies: 5
Views: 26859

You can define local and global risks for both task and resources. To define local risks to resources: 1. Go to resource view 2. Click on resource ID, resource information dialog comes up 3. Go to Risks tab 4. Enter risks To define global risks: 1. Go to Global risks view 2. Enter risks 3. Assign ri...
by Intaver Support
Sun Mar 11, 2007 10:06 am
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Resource risks
Replies: 1
Views: 16784

You can assign risks to resources the same way as you assign risk to tasks. Here is the difference. The risk may occur in all tasks this risk is assigned to. If resource is used on 50% for the particular task, probability of the risk will reduce on 50%.