Search found 992 matches

by Intaver Support
Thu Sep 14, 2023 7:25 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Cumulative Costs
Replies: 1
Views: 2213

Re: Cumulative Costs

Yes, but you will need to use the integration with Excel. To view a cumulative costs. 1. Run a simulation. 2. Open the Cost Analysis view. 3. In the View, in the left pane, select all of the activities up to the milestone that you want to view the cumulative costs. 4. From the File menu, click Expor...
by Intaver Support
Thu Sep 14, 2023 7:21 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Modifying Seed values
Replies: 1
Views: 3273

Re: Modifying Seed values

Yes, RiskyProject has seed values for each task can be viewed and modified in the Project View as columns. By default they are not shown, but can be added to a view by right clicking on a column header and using the Insert command. From the example below, you can see that RiskyProject sets Seed valu...
by Intaver Support
Thu Sep 14, 2023 7:19 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Calculated Risk Probability
Replies: 1
Views: 2970

Re: Calculated Risk Probability

Risk probability is not simply a input value (e.g 50%). At each iteration, the risk has the input chance that it will occur. It is very similar to flipping a coin. If on your first turn it is heads, what is the probability that on the 2nd turn it will be tails? It is 50% for every additional turn. S...
by Intaver Support
Thu Aug 24, 2023 11:18 am
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Cost/Benefit Analysis
Replies: 7
Views: 42581

Re: Cost/Benefit Analysis

We are currently working on RiskyProject version 8 and considering including decision tree analysis. It will go only to RiskyProject Professional.
by Intaver Support
Thu Aug 24, 2023 11:16 am
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Task Resource Allocation Units
Replies: 2
Views: 17167

Re: Task Resource Allocation Units

With regards to overallocation RiskyProject works very similarly to Microsoft Project and other scheduling software. Particularly RiskyProject offer resource allocation chart which shows resource allocation and overallocation during certain period of time. The main specific feature of RiskyProject i...
by Intaver Support
Thu Aug 24, 2023 11:12 am
Forum: Project Portfolio Risk Management
Topic: Advantages of RiskyProject Enterprise
Replies: 1
Views: 18616

Re: Advantages of RiskyProject Enterprise

Many our clients are currently switching from RiskyProject Professional and RiskyProject Lite to RiskyProject Enterprise. If you already have a number of licenses for RiskyProject Professional and RiskyProject Lite you don't need to purchase and install these modules again. You just need to install ...
by Intaver Support
Mon Aug 07, 2023 12:49 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Project Control in RiskyProject
Replies: 1
Views: 1978

Re: Project Control in RiskyProject

In RiskyProject you can perform project risk analysis on any phase of the project based on information from project control. Here is the process: 1. In Microsoft Project, Oracle Primavera or any other software where you maintain the original project schedule, you can enter information about % percen...
by Intaver Support
Mon Aug 07, 2023 12:14 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Assigning a multiday delay to a one day task
Replies: 1
Views: 3113

Re: Assigning a multiday delay to a one day task

You would need to use Fixed Duration Delay (5 to 10 days) rather than Relative Delay. It is possible to model a 500% - 1000% relative delay as well.
by Intaver Support
Mon Aug 07, 2023 12:12 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License activation error
Replies: 1
Views: 2313

Re: License activation error

RiskyProject allows three activations of one license. If you are moving RiskyProject license from one computer to another and you exceed number of actication allowed, you will receive a message "License has already been activated". In this case you need to contact Intaver Institute and we will help ...
by Intaver Support
Thu Jul 27, 2023 1:08 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Setting a statistical distribution for group of tasks
Replies: 2
Views: 14513

Re: Setting a statistical distribution for group of tasks

We recommend to use Uncertainty Bands for settings distributions for cost and duration for the group of tasks. Such approach makes setting uncertainties most consistent across the project. In case of RiskyProject Enterprise uncertainty band information is saved in RiskyProject database, which makes ...
by Intaver Support
Thu Jul 27, 2023 1:04 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: Criticality Index
Replies: 2
Views: 14040

Re: Criticality Index

After the column with the criticality index is inserted to the grid, the grid information will be saved in to ALM file. So when you reopen project file this column will be presented. It is also possible to save column layout for all future new projects. It is done using Schedule -> Project Options -...
by Intaver Support
Thu Jul 27, 2023 12:58 pm
Forum: Project Portfolio Risk Management
Topic: Schedule Reports that show Uncertainty Bands.
Replies: 2
Views: 12823

Re: Schedule Reports that show Uncertainty Bands.

It is important to note that all information about Uncertainty Bands in RiskyProject Enterprise are saved into the Enterprise database. As a result the users in one organization will be able to share settings for the uncertainty bands. Only administrator are able the edit and save these settings. Th...
by Intaver Support
Mon Jul 03, 2023 10:09 pm
Forum: RiskyProject: Project risk management and risk analysis software
Topic: Viewing or Converting Labour Days to Calendar Days
Replies: 1
Views: 3531

Re: Viewing or Converting Labour Days to Calendar Days

Calendar days are referred to as “elapsed days” or edays. Use of elapsed duration setting in the Advanced Settings in the desktop version when you import schedule from Microsoft Project. It is because the letter that is used to denote elapsed days is dependent upon the language settings. http://www....
by Intaver Support
Mon Jul 03, 2023 10:03 pm
Forum: RiskyProject Project Risk Analysis Software Issues
Topic: License Activation Already Activated Message
Replies: 1
Views: 2538

Re: License Activation Already Activated Message

We can refresh the license, but this will continue to happen as it appears that the license information cannot be written to your computers registry. Typically this occurs when there are insufficient user permissions to write to the license information to the registry, a utility is removing "unautho...
by Intaver Support
Mon Jul 03, 2023 5:49 pm
Forum: Project Risk Analysis and Project Risk Management Theory
Topic: Pre and Post-Mitigation Simulation Results
Replies: 1
Views: 2775

Re: Pre and Post-Mitigation Simulation Results

The problem appears to be that you have not created a post mitigated baseline with reduced probabilities etc due to the mitigation activities. Assigning mitigation activities in the waterfall chart are only a forecast but do not impact the simulation results. To create a post mitigated baseline, you...