With latest updates of RiskyProject, sorting and filtering columns is now available. On the top of each column there is a down arrow, that allows you to sort/filter based on the data.
Search found 998 matches
- Sat Oct 08, 2022 8:17 pm
- Forum: Project Portfolio Risk Management
- Topic: Sorting and Filtering columns
- Replies: 1
- Views: 11422
- Sat Oct 08, 2022 8:08 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: License already activated message
- Replies: 1
- Views: 11157
Re: License already activated message
You are most likely seeing this as you have previously activated the license on another computer. RiskyProject desktop software is a perpetual license that is associated with a license key. Under the End User License Agreement, the license can only be activated on one computer, unless dispensation i...
- Sat Oct 08, 2022 7:05 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Trial period extension
- Replies: 1
- Views: 12289
Re: Trial period extension
Yes, upon request we can provide an extended evaluation license that will allow you to complete your evaluation of the software. Contact support@intaver.com and request an extended evaluation license.
- Wed Aug 03, 2022 3:23 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Criticality Index
- Replies: 1
- Views: 11987
Re: Criticality Index
1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com) 2. Add the criticality index column to the Result Gantt view. https://www.intaver.com/images/PR_...
- Wed Aug 03, 2022 3:18 pm
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Start as late as possible constraint
- Replies: 1
- Views: 9357
Re: Start as late as possible constraint
Start as late as possible are used for a variety of management purposes, but are not used in SRA best practices. While I cannot comment on their use in your schedule usually they are used to model late procurement (pay as late as possible), but they should not be on the critical path. We have a simi...
- Wed Aug 03, 2022 3:18 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject fails to launch after upgrade to 7.2
- Replies: 1
- Views: 10433
Re: RiskyProject fails to launch after upgrade to 7.2
Most likely this is a registry issue. The IT update probably corrupted the registry entry for RiskyProejct. You can reset the registry by deleting the RiskyProject registry entry. 1. To open the registry editor, press the Windows key and type “regedit” in the Search field. 2. Launch the Registry Edi...
- Fri Jun 17, 2022 12:21 pm
- Forum: Project Portfolio Risk Management
- Topic: Edit or modify the Risk Dashboard
- Replies: 1
- Views: 14589
Re: Edit or modify the Risk Dashboard
To start with an empty dashboard, right click on the dashboard and click Clear Dashboard. https://www.intaver.com/images/RP_Forum_RiskDashboard1.png However, it can be useful to reuse some of the existing elements. In this case, you may want do a comparison between the current dashboard and your tem...
- Fri Jun 17, 2022 12:13 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Visualizing Multiple Baselines
- Replies: 1
- Views: 15238
Re: Visualizing Multiple Baselines
The issue is that you can create baselines with and without the results of the analysis. If the results of the simulation are not saved with the baseline, the baseline will not appear as a cumulative probability plot. When you create a baseline, the procedure must be followed exactly to save the res...
- Tue May 17, 2022 11:26 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Customizing Uncertainty Bands
- Replies: 1
- Views: 11858
Re: Customizing Uncertainty Bands
You are correct, uncertainty bands to calculate Low, Most Likely, and High durations and costs for activities based on your assessments of the inherent risk that tasks have. The dialog that allows you to modify the uncertainty bands is located on the Risk tab > Distribution group. 1. Click the Uncer...
- Tue May 17, 2022 11:21 am
- Forum: RiskyProject Project Risk Analysis Software Issues
- Topic: Large master schedule
- Replies: 1
- Views: 14642
Re: Large master schedule
Without using a 3rd party tool such as MS Project that support master schedules, you have a couple of options 1. Create simplified models of each project as subtasks in a program schedule. For example each project could be rolled up to level 3 activities. You would then apply risks and uncertainties...
- Wed May 04, 2022 12:12 pm
- Forum: Project Portfolio Risk Management
- Topic: RiskyProject Enterprise 7.2
- Replies: 0
- Views: 20089
RiskyProject Enterprise 7.2
Intaver Institute released new version of RiskyProject Enterprise software. RiskyProject Enterprise 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully c...
- Wed May 04, 2022 12:09 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: RiskyProject 7.2 is released
- Replies: 0
- Views: 20912
RiskyProject 7.2 is released
Intaver Institute released new version of RiskyProject software. RiskyProject 7.2 is a major release which includes the following new features: 1. New Risk Dashboard: present hundreds of different key performance indicators (KPIs) and charts related to your risks with a fully customizable Risk Dashb...
- Mon Mar 14, 2022 8:07 pm
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Isolating impact of Risk Events and Uncertainties
- Replies: 1
- Views: 12466
Re: Isolating impact of Risk Events and Uncertainties
To Isolate the impacts of uncertainties you can disable all risks in the Risk ribbon. https://www.intaver.com/images/RP_Forum_RibbonUncertainties.png To isolate the impact of uncertainties is more difficult. I would recommend making a copy of the file and then in the Project view, select all the act...
- Mon Mar 14, 2022 8:03 pm
- Forum: RiskyProject: Project risk management and risk analysis software
- Topic: Windows 11 Compatibility
- Replies: 1
- Views: 13352
Re: Windows 11 Compatibility
Yes, all versions of RiskyProject (Lite, Professional, and Enterprise) are compatible with Windows 11.
- Fri Jan 28, 2022 9:54 am
- Forum: Project Risk Analysis and Project Risk Management Theory
- Topic: Post-mitigation impact calculation
- Replies: 1
- Views: 13283
Re: Post-mitigation impact calculation
RiskyProject takes post-mitigation probability, impacts and scores shown in Risk Register from Waterfall tab of Risk Information dialog. It is the last line, or last mitigation plan, defined by user. Risk register can also display post-mitigation probabilities, impacts and scores for individual cate...