Using custom or discrete distributions with limited data.

General discussion and questions about project risk management and risk analysis software RiskyProject

Moderator: Intaver Support

Kathy
Posts: 14
Joined: Sat Nov 26, 2005 11:06 am
Location: London, UK

Using custom or discrete distributions with limited data.

Postby Kathy » Sun Apr 16, 2017 7:55 pm

- I have actual data for task duration, but only 5 samples. Should I use a custom or discrete distribution or is the data to limited?

Intaver Support
Posts: 713
Joined: Wed Nov 09, 2005 9:55 am

Re: Using custom or discrete distributions with limited data.

Postby Intaver Support » Sun Apr 16, 2017 7:56 pm

This is a difficult question to answer as you haven’t provided any details about the nature of the tasks. In this circumstance, normally this would not be considered enough data with which to construct a reliable distribution. Most likely with such a limited data set, you will have a good indicators for what the boundary conditions should be (Low and High) or where your Most Likely lies. In this case, I would lean more heavily on your SME’s experience as to setting a distribution.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject