Restore a previous baseline

General discussion and questions about project risk management and risk analysis software RiskyProject

Moderator: Intaver Support

Dwen
Posts: 10
Joined: Sat Jun 05, 2010 4:50 am

Restore a previous baseline

Postby Dwen » Fri May 05, 2017 3:02 pm

How can I restore previous baseline (baseline which I created before)?

Intaver Support
Posts: 728
Joined: Wed Nov 09, 2005 9:55 am

Re: Restore a previous baseline

Postby Intaver Support » Fri May 05, 2017 3:04 pm

In RiskyProject, if have deleted a baseline, it cannot be “restored”. If by restoring, you mean loading an existing baseline, you need to go to the Schedule tab > Baselines >Manage Baselines.
To load a baseline you must click the Current baseline checkbox associated with it. Once you select the baseline you want to restore, click OK and it will be loaded into RiskyProject (schedule, resources, costs, and risks).

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com


Return to “RiskyProject: Project risk management and risk analysis software”

Who is online

Users browsing this forum: No registered users and 1 guest