Statistical distribution for lag

Post by G.K.Jun » Thu Mar 03, 2016 10:29 am

Can I assign risk event to lag? How to assign statistical distribution to lag?
G.K.Jun, program manager, Harrisonburg, VA, USA

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Statistical distribution for lag

Post by Intaver Support » Thu Mar 03, 2016 10:33 am

You cannot assign a risk directly to a lag however, you can assign a statistical distribution to lag between predecessor and successor. This uncertainty in the duration of the lag is then accounted for during the Monte Carlo simulation.

Image

To assign uncertainty to lags, open the Task Information dialog box and click the Predecessors tab. Here you can set lags. By default it is zero, but you can assign Low, Base, and High estimates for the lag If you enter low and high estimates, you must also select a distribution type.