Viewing Project results for Work

Posted: Tue Nov 15, 2016 2:46 pm
by Nathan
Is it possible to create a chart that shows results for Work (#of hrs or effort) for the entire project?

Re: Viewing Project results for Work

Posted: Tue Nov 15, 2016 2:48 pm
by Intaver Support
Yes, if you have a resource loaded schedule, work for all resources, tasks, and the project is calculated during the Monte Carlo simulation.
To view Work for the entire project:

1. Run a simulation.
2. Open Analysis > Project Summary.
3. Click Statistical Data for Work (lower right). A chart showing the probabilistic results for work opens.

The chart can be a histogram, cumulative probability, or as in the example below, a combination of the two.
The work data or statistics can be copied for use in other programs by right-clicking and using shortcut menu.

Image

Re: Viewing Project results for Work

Posted: Thu Jan 05, 2017 11:24 am
by Fer23
I found that chart from my version of RiskyProject is different than on the screen shot. Is it a new version?

Re: Viewing Project results for Work

Posted: Thu Jan 05, 2017 11:26 am
by Intaver Support
This chart is coming from RiskyProject 7 beta version. New version will be released at the beginning of the year.