Page 1 of 1

All risks report

Posted: Fri Dec 15, 2017 4:30 pm
by Rtgorwer
How to I use All Risks reports in Report tab?

Re: All risks report

Posted: Fri Dec 15, 2017 4:32 pm
by Intaver Support
If you are running quantitative risk analysis and need to understand how the risks have been assigned to a project, the Report: All Risks is superior to the Risk Register. The Report: All Risks is one of the standard reports that came out with our first version. It is an extremely valuable report if you need to present and justify your risk model. It can be printed out directly from RiskyProject or exported as a csv file if you would like to import into another application.

To open the Report: All Risks go to the Report tab > Report: All Risks.

You can customize the report to include General Information, Risk Properties, Risk Assignments, and the Moment of Risk.

Image