Resource Leveling

Posted: Sun Mar 15, 2020 9:35 pm
by katto1
How can I level resources in RiskyProject?

Re: Resource Leveling

Posted: Sun Mar 15, 2020 9:39 pm
by Intaver Support
RiskyProject does not support resource leveling. Probabilistic resource leveling would most likely not provide a valid result and in most cases would be technically unfeasible due computer performance and differing leveling algorithms that are used by different scheduling software. This refers to how resources are managed. For example if a resource is the first to start on an activity, during leveling should it be the first to be reallocated or the last? If resource leveling is required, we recommend exporting the results of the simulation to a scheduling software such as MS Project or Primavera P6.

RiskyProject can read data from resource leveled schedules. Here is how to do it:
viewtopic.php?f=4&t=1180&p=2460&hilit=Leveling#p2460