Exporting RiskyProject results to Primavera P6

Posted: Wed Apr 22, 2020 4:51 pm
by KerryMiller
Is any way to export results of RiskyProject risk analysis back to Primavera P6?

Re: Exporting RiskyProject results to Primavera P6

Posted: Wed Apr 22, 2020 5:02 pm
by Intaver Support
There are a number of way to do it:

1. Use Microsoft Project XML export format. Go to File -> Export -> XML. Save results to the file and import it to Primavera P6. You can export deterministic project schedule or result of risk analysis associated with certain percentile.

2. Use Excel Export then Import the *.xls to p6. Then map fields and open Excel file in P6.

Here is how export look in RiskyProject Enterprise: