Setting a statistical distribution for group of tasks

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
DavidB
Posts: 18
Joined: Thu Nov 24, 2005 3:44 pm
Location: Denver, CO

Setting a statistical distribution for group of tasks

Post by DavidB » Tue Dec 21, 2021 4:46 pm

We have imported our schedule with our estimates. By default it appears that Triangular distributions are set. Is there anyway to mass edit the distribution type to another distribution
David B

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Setting a statistical distribution for group of tasks

Post by Intaver Support » Tue Dec 21, 2021 4:51 pm

To quickly change the distribution type, you can use the Set Low/High Duration dialog box. This dialog only updates those values that have been modified in the dialog box. For example if you only change the statistical distribution, no other task data will be modified.
To modify the statistical distribution for a 2 or more activities:

1. Open the Project View.
2. Select the tasks you want to modify. .
3. Right-click on a Task ID.
4. Select Set Low/High Duration or Low/High Fixed Cost.
5. Select a distribution from the drop-down list.
6. Click OK to apply changes.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Setting a statistical distribution for group of tasks

Post by Intaver Support » Thu Jul 27, 2023 1:08 pm

We recommend to use Uncertainty Bands for settings distributions for cost and duration for the group of tasks. Such approach makes setting uncertainties most consistent across the project. In case of RiskyProject Enterprise uncertainty band information is saved in RiskyProject database, which makes setting distribution for the group of tasks consistent across the organization.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com