Viewing or Converting Labour Days to Calendar Days

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Ken
Posts: 65
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Viewing or Converting Labour Days to Calendar Days

Post by Ken » Mon Jul 03, 2023 10:02 pm

I have a chronogram and by default RiskyProject by default uses labour days for base duration. I would to show the calendar days. ¿How is it possible to get that?
Ken the PM

Intaver Support
Posts: 995
Joined: Wed Nov 09, 2005 9:55 am

Re: Viewing or Converting Labour Days to Calendar Days

Post by Intaver Support » Mon Jul 03, 2023 10:09 pm

Calendar days are referred to as “elapsed days” or edays. Use of elapsed duration setting in the Advanced Settings in the desktop version when you import schedule from Microsoft Project. It is because the letter that is used to denote elapsed days is dependent upon the language settings.

http://www.intaver.com/Help4/RP_Help.ph ... pping.html

Image

You can "switch" to elapsed days in your schedule by adding letter 'e' before time units.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply