Assigning a multiday delay to a one day task

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
KerryMiller
Posts: 23
Joined: Tue Dec 18, 2007 3:39 pm
Location: USA, MI

Assigning a multiday delay to a one day task

Post by KerryMiller » Mon Aug 07, 2023 12:13 pm

I have a risk that that the Site Handover might get delayed even with 2 weeks.

If I want to simulate this/ I can set a relative delay even with 85% probability and 70% percent outcome, but the program considers the duration of the task and not the start date of the task. How can I set up that the program can simulate 1-2 weeks possible delay of 1 day activities? It went up only to 1,7 days.
Project Engineer

Intaver Support
Posts: 995
Joined: Wed Nov 09, 2005 9:55 am

Re: Assigning a multiday delay to a one day task

Post by Intaver Support » Mon Aug 07, 2023 12:14 pm

You would need to use Fixed Duration Delay (5 to 10 days) rather than Relative Delay. It is possible to model a 500% - 1000% relative delay as well.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com