Assign risk to summary tasks

Posted: Mon Jun 16, 2014 4:30 pm
by ProjectM
How can assign risk "Increase duration" or "increase cost" to the summary task?

Re: Assign risk to summary tasks

Posted: Mon Jun 16, 2014 4:36 pm
by Intaver Support
You cannot assign risk for the summary task directly. It is because ambiguity in distributing risk outcome between different subtasks. For example you have summary task A which has two sequential subtasks B and C. If you increase duration of task A due to certain risk, it is unclear how duration of tasks B and C will increase. We recommend to assign risk to subtask. You can assign risk to all subtasks using 'Drag'n'drop' risk view. This way you can select a summary task, but actually risk will be assigned to the subtasks.

Re: Assign risk to summary tasks

Posted: Sun Aug 17, 2014 4:22 pm
by ProjectM
We use RiskyProject version 5? Can we use risk drag'n'drop view to assign risks to summary tasks?

Re: Assign risk to summary tasks

Posted: Sun Aug 17, 2014 4:24 pm
by Intaver Support
RiskyProject drag'n'drop view is only available in RiskyProject version 6. You need to upgrade version 5 to version 6.