Moving project start times
We have old project schedules that we use as templates, but need to shift the start dates for new projects, can we do this in RiskyProject?
Ken the PM
-
- Posts: 995
- Joined: Wed Nov 09, 2005 9:55 am
Re: Moving project start times
Yes, you can shift the project start times forward in RiskyProject by resetting the Project Start date in the Project Settings.
To shift the project start times, on the Schedule tab go to Settings and Options > Project Settings. Click in the Project Start time box, and select a new project start time. You can also manually edit the date to update the project start time.
Note: If your project has any hard constraints, such as must start on or finish on, this will prevent the project from shifting successfully. We recommend all constraints be set to As soon as possible.
To shift the project start times, on the Schedule tab go to Settings and Options > Project Settings. Click in the Project Start time box, and select a new project start time. You can also manually edit the date to update the project start time.
Note: If your project has any hard constraints, such as must start on or finish on, this will prevent the project from shifting successfully. We recommend all constraints be set to As soon as possible.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com