Primavera integration task links

Posted: Fri Dec 16, 2016 5:40 pm
by NTT
Unlike MS Project, Primavera supports tasks that have both FF and SS link between them. Is this supported in RiskyProject?

Re: Primavera integration task links

Posted: Fri Dec 16, 2016 5:41 pm
by Intaver Support
RiskyProject will import a schedule that has two tasks that are linked with both SS and FF relationships. However, because RiskyProject does not natively allow users to create these types of links, it will ignore one of the links.