Maximum number of risks

Posted: Mon Mar 05, 2018 10:00 am
by Nathan
What is the maximum number of risks in RiskyProject?

Re: Maximum number of risks

Posted: Mon Mar 05, 2018 10:01 am
by Intaver Support
Theoretically there is no maximum number of risks. However, the question is what value is being produced by having hundreds of risks listed in your risk register. The reason why we list them is so that they can be managed, and it is if not impossible, extremely difficult to manage hundreds of risks. If it is the case that you do have hundreds of risks that have to be managed, it may be indicating that the project needs to be broken down into smaller more manageable subprojects. In this case, risks which only impact specific deliverables can be managed at the appropriate level: whereas, risks that can impact the entire program can be managed at a higher level. The is the underlying methodology behind RiskyProject Enterprise.

Re: Maximum number of risks

Posted: Thu Oct 25, 2018 11:31 am
by Jason
I tried around 100 risks, and it does not cause any reduction of RiskyProject performance. The issue is it is hard sometimes to find a risk and people sometimes enter the same risk multiple times with a similar name.