Modifying the number of hours or days make up days, weeks and months.

Posted: Tue May 01, 2018 11:10 am
by G&G
How can I adjust number of hours per day, days in month, and hours per week?

Re: Modifying the number of hours or days make up days, weeks and months.

Posted: Tue May 01, 2018 11:12 am
by Intaver Support
In the Project Options > Calendar tab you can define the number of hours/day, hours/week, and days/month.
To set as default values for all new projects, click the Set as default button.

Image

Re: Modifying the number of hours or days make up days, weeks and months.

Posted: Tue May 01, 2018 11:14 am
by G&G
If I use schedule from Microsoft Project, does RiskyProject import this settings from the schedule, created in Microsoft Project?

Re: Modifying the number of hours or days make up days, weeks and months.

Posted: Tue May 01, 2018 11:14 am
by Intaver Support
Yes. It does.