Page 1 of 1

Multiple Currencies

Posted: Wed May 16, 2018 4:28 pm
by Rtgorwer
You can only use a single currency for any single project. You can change currencies for different projects.

Re: Multiple Currencies

Posted: Wed May 16, 2018 4:34 pm
by Intaver Support
You can only use a single currency for any single project. You can change currencies for different projects.
You can set the currency used for the project in the Project Options > Cost tab.

Image

Re: Multiple Currencies

Posted: Thu Jul 16, 2020 12:27 pm
by Intaver Support
It is important to know that RiskyProject has only one currency for project portfolio (for RiskyProject Enterprise) and for whole project (for RiskyProject Lite and RiskyProject Professional). It may cause some incompatibility with Primavera P6 which uses multiple currencies.