Calculation of risk outcome

Posted: Tue Jul 11, 2006 4:52 pm
by Jim Doyle
I'm using RiskyProject for about one year. I have a question about risks:

I have two local risks "20% delay". They occur at the same time. What would be the total delay of the task?

Posted: Tue Jul 11, 2006 4:59 pm
by Intaver Support
Here is how it works:

Assume that task duration is 5 days. Risk A causes 20% delay (1 day) and risk 2 causes 20% delay (1 day). Total delay will be 2 days.

New version of RiskyProject has risk called "Execute mitigation plan". Mitigation plan has own outcome, e.g. delay 20%. If two risks "Execute mitigation plan" occurred at the same time for the same task, task will be delayed only on 20% (not 40%).