Cannot delete fixed cost

Post by Daniel » Tue Aug 15, 2006 4:40 pm

When I select fixed cost for the particular task and then press DELETE, cost does not change.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Aug 15, 2006 5:53 pm

In order to set cost, duration, or income (in RiskyProject 2) to zero, just enter zero instead of current value. You cannot delete value in the grid to set it to zero.