How can I display a tornado diagram with most important tasks in RiskyProject?

Posted: Thu Oct 05, 2006 3:37 pm
by Intaver Support
Sensitivity Analysis in RiskyProject produces a Tornado Diagram. Sensitivity Analysis shows you the input parameters (task duration, start and finish time, success rate, etc.) that have the most impact on project parameters (total project cost, total duration, project finish time, and success rate). Sensitivity analysis also allows you to identify critical risks, which have the potential of significantly affecting your project. These critical risks should be the key focus of your risk mitigation efforts. The results of sensitivity analysis are presented in sensitivity charts.

Re: Tornado Diagram

Posted: Thu Aug 13, 2020 11:10 am
by Intaver Support
Risks in the integrated Risk Register are also ranked based on sensitivity to major project parameters and risk scores can be presented similarly as a Tornado chart, with horizontal bars. Risks can be ranked based on specific project parameters or on a "normalized' impact score across all project parameters.