Risk project limitations

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
remerson risk analysis
Posts: 8
Joined: Wed Feb 07, 2007 1:55 pm
Location: Ottawa, ON

Risk project limitations

Post by remerson risk analysis » Wed Feb 07, 2007 4:02 pm

I'm trying to import schedule from Primavera to RiskyProject. The project has around 10000 activities. Can I do so?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Wed Feb 14, 2007 12:48 pm

RiskyProject has la imitation: you cannot create more than 5000 activities. However in RiskyProject 3.0 we are planning to remove this limitation.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com