Low and high duration for group of tasks

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Jason
Posts: 38
Joined: Wed Nov 09, 2005 10:46 pm

Low and high duration for group of tasks

Post by Jason » Tue Dec 04, 2007 5:29 pm

I would like to assign low duration -10% and high duration +10% for a group of task as the same moment. I tried to use options function, but apparently it works only for new tasks. What if I have 10 tasks I imported from MS Project?
Jason

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Dec 04, 2007 5:45 pm

Automatic calculation low and high duration in RiskyProject works for new tasks only. In this case coefficient or absolute increment (in duration units or currency units) can be entered in Tools->Options.

If you edit existing tasks or import data from MS Project, you will need to update low and high duration or cost each task individually. RiskyProject version 3 will have option to update low and high duration for many tasks at the same moment.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support » Tue Feb 19, 2008 4:33 pm

This feature is currently implemented in RiskyProject 3. If you wish to try it please feel free to request beta version of the RiskyProject 3. Just send us e-mail to sales@intaver.com or info@intaver.com.

Please note that we implemented not only automatic calculation of low and high duration, but also low and high fixed cost.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com