Low and high duration for group of tasks

Posted: Tue Dec 04, 2007 5:29 pm
by Jason
I would like to assign low duration -10% and high duration +10% for a group of task as the same moment. I tried to use options function, but apparently it works only for new tasks. What if I have 10 tasks I imported from MS Project?

Posted: Tue Dec 04, 2007 5:45 pm
by Intaver Support
Automatic calculation low and high duration in RiskyProject works for new tasks only. In this case coefficient or absolute increment (in duration units or currency units) can be entered in Tools->Options.

If you edit existing tasks or import data from MS Project, you will need to update low and high duration or cost each task individually. RiskyProject version 3 will have option to update low and high duration for many tasks at the same moment.

Posted: Tue Feb 19, 2008 4:33 pm
by Intaver Support
This feature is currently implemented in RiskyProject 3. If you wish to try it please feel free to request beta version of the RiskyProject 3. Just send us e-mail to sales@intaver.com or info@intaver.com.

Please note that we implemented not only automatic calculation of low and high duration, but also low and high fixed cost.