Post by MichaelTR » Wed May 19, 2010 9:19 pm

When I open the risk chart view all the task bubbles are centered in the middle of the chart.

Is there a reason for this or is this a bug?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Risk chart issue

Post by Intaver Support » Wed May 19, 2010 9:23 pm

Obviously the risk chart is a bubble chart, and the most likely reason why they are all centered in the middle is that you are viewing Total Task Cost (vs Total Task Duration). If there are costs associated with the activities the you will see the activites all located on the (0,0) axis. Switch to Task Duration as the metric and the risk chart should display correctly.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Jason
Posts: 38
Joined: Wed Nov 09, 2005 10:46 pm

Re: Risk Chart

Post by Jason » Thu Mar 07, 2013 11:14 am

When I print risk (bubble) chart diameter of bubbles does it seem to be too small. The location of circles is correct. Relative diameter of each circle representing cost or duration is also correct. I recommend increasing diameter of circles for printing.
Jason

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support » Thu Mar 07, 2013 11:18 am

Thank you for your suggestion. We will adjust the diameter of the circle in the upcoming release for printing. Please note that may also copy chart to clipboard to paste it to other software, such as PowerPoint.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Fer23
Posts: 19
Joined: Tue Apr 10, 2007 8:22 am
Location: USA
Contact:

Re: Risk Chart

Post by Fer23 » Wed Jun 12, 2013 5:42 pm

In Risk chart I never saw red or yellow circles. When red or yellow circles suppose to appear?
Project risk management, decision and risk analysis

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support » Wed Jun 12, 2013 5:53 pm

Most likely you have project schedule with balanced risks: siginificant risks are assigned to task with longer duration or higher cost.

Here is some information about risk chart and how risk chart supposes to look like:
http://www.intaver.com/Help4/RP_Help.ph ... Chart.html
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Re: Risk Chart

Post by Rtgorwer » Sun Sep 15, 2013 10:32 am

Is possible to print Risk Chart?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support » Sun Sep 15, 2013 10:41 am

Yes. You can print Risk Chart.

Simply open Risk Chart (Analysis Tab). Click on File -> Print or File -> Print Preview.