Risk is 100% mitigated

Postby Tomico » Thu Nov 23, 2017 11:05 am

Is there any way to specify that risks which are mitigated 100% by the mitigation plan should not be used in the calculation?

Intaver Support
Posts: 728
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk is 100% mitigated

Postby Intaver Support » Thu Nov 23, 2017 11:10 am

If risks are 100% mitigated, then they are no longer active and can be closed. To close a risk, open the Risk Register, select the risk and double-click on the Risk ID (far left column).

In the Risk Information dialog box > Properties > click the Closed option.

Image

You can also sent probability the risk equals 0. It can be reflected in Risk waterfall chart of Risk Information dialog box: risk probability after mitigation can be equal zero.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com


Return to “Project Risk Analysis and Project Risk Management Theory”

Who is online

Users browsing this forum: No registered users and 3 guests