Cost resources

Posted: Wed Jan 06, 2016 3:12 pm
by Tomico
When should I use cost resources and how would it affect risk analysis?

Re: Cost resources

Posted: Wed Jan 06, 2016 3:25 pm
by Intaver Support
In RiskyProject cost resources is developed for compatibility with Microsoft Project and other scheduling software. So if your schedule in Microsoft Project has cost resources it will be shown in RiskyProject as cost resources after important. Some organizations actively use cost resources as part of project scheduling process. It may help to facilitate earned value management.

Image

There are no risk events, which affect cost resource directly. If cost resource is assigned to the task, cost of the cost resource is a properly of resource assignment. It is important to note that cost of cost resource assignment does not depend on task duration. For example, if your task duration is between 3 to 7 days and you have cost resource with cost $5000 assigned to this task, the cost of the task will be always $5000. On statistical distribution of the cost for this task you would see only one bar. Therefore you need to be vary careful when you switch resource type from cost to work and vice versa. Cost of work resources depends on duration of task.