P10 and P90 percentiles on frequency historgrams

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Expert
Posts: 7
Joined: Sun Jul 09, 2006 11:11 pm

P10 and P90 percentiles on frequency historgrams

Post by Expert » Wed Jan 20, 2016 11:24 am

How can a present P10 and P90 percentiles on frequency and cumulative probability plots in RiskyProject?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: P10 and P90 percentiles on frequency historgrams

Post by Intaver Support » Fri Jan 29, 2016 5:47 am

In current version of RiskyProject for each frequency and cumulative probability plots we have a slider at the top of the bar. You can move this slider and see a probability associated with certain value. For example, you can see that there is a 60% chance that project of task will be completed in 20 days. This way you can see value associated with P10 or P90. In next versions in addition to this slider we are going to how line associated with particular probability, such P10 and P90. It will be separate lines independent of slider, so slider will remain as it is.

You have an options to enable/disable this slider. To do it just right click on the chart and selection options. Format Chart dialog box will come up. You can check or uncheck option "Slider". The chart will be re-drawing with or without this slider.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply