Viewing results of simulations as percentiles on Gantt chart

This forum includes discussion about project risk analysis and risk management theory: Monte Carlo simulations, Event Chain Methodology, schedule and cost risk analysis. Please submit questions and case studies about your experience with our project risk analysis software.

Moderator: Intaver Support

Post Reply
Bergman
Posts: 12
Joined: Sat Nov 26, 2005 12:00 pm
Location: New York

Viewing results of simulations as percentiles on Gantt chart

Post by Bergman » Wed May 04, 2016 11:24 am

The Result Gantt seems to show two bars for each activity: original schedule and the Mean results. As well the distribution is shown for start and finish times for low and high. Is there anyway that we can just show the Blue bar as specific percentage?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Viewing results of simulations as percentiles on Gantt chart

Post by Intaver Support » Wed May 04, 2016 11:27 am

By default, the Result Gant shows the deterministic schedule as a white bar and the Results as a blue bar. The results (blue) bar by default shows the mean value (Start or Finish Time). However, if you right-click on the Gantt Chart, you can switch the results bar to either Low or High results. In the example below, we have selected the High results and which are show as a darker blue by default.

Image

The Low and High results are percentiles or certainty levels and are defined in the Project Options > Calculation dialog box. In the example below, if you choose Show High Results, the Result Gantt will use P70 for the blue bar.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com