Define distribution for start time of the task

Posted: Tue Oct 04, 2016 9:54 pm
by DavidB
Is it possible to set uncertainties for task start times?

Re: Define distribution for start time of the task

Posted: Tue Oct 04, 2016 9:58 pm
by Intaver Support
Yes, however cases in which this can be used are limited such as the first activity in the project as otherwise start times are a product of the precedent network. To set uncertainty for start times on a activity, right-click on the activity ID and choose Task Information.

- In the General tab, set Low (early) and High (late) start times for the activity.

Image

- Click the Distributions tab.
- Select the Start Time sub tab.
- Select a distribution from the Distribution drop down list. The shape and parameters of teh charted in the Probability Density chart to the right.
- Depending upon the distribution type, you can modify parameters (e.g. Most Likely)
- Click OK to assign the distribution.

Re: Define distribution for start time of the task

Posted: Fri Nov 04, 2016 2:10 pm
by Fer23
How can I see output distributions in RiskyProject Lite?

Re: Define distribution for start time of the task

Posted: Fri Nov 04, 2016 2:14 pm
by Intaver Support
You cannot see output distributions (frequency charts, cumulative probability plots, etc.) in RiskyProject Lite. The exception is RiskyProject Add-in in Microsoft Project, where you can distributions for finish time, cost, and duration of project. We recommend you to upgrade to RiskyProject Professional.