NPV calculation

Post by G.K.Jun » Mon Dec 12, 2016 4:25 am

How can I calculate the project NPV?
G.K.Jun, program manager, Harrisonburg, VA, USA

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: NPV calculation

Post by Intaver Support » Mon Dec 12, 2016 4:32 am

NPV calculation is a feature of the Cashflow view. If your project has both costs and income, the Cashflow view will present a cash flow chart as well as the calculated NPV for both the original plan and with risks and uncertainties. To calculate the NPV enter a discount rate in the Discount Rate box. Once you have a discount rate, during the simulation, RiskyProject will calculate both the NOV and the IRR (Internal Rate of Return).